| Course | QSO 640 Project Management |
|---|---|
| Module | Module 6 |
| Paper type | graduate assignment building a cost baseline with contingency and reserves, then applying earned value and earned schedule at a status date to diagnose variances, forecast cost and completion and recommend corrective action |
| Length | About 1,260 words, 7 pages |
| Format | APA 7 student paper |
| School | Southern New Hampshire University |
| Program | MS Project Management |
| Updated | October 2026 |
Free sample paper for QSO 640 Module 6
Below Plan and Still in Trouble: The Cost Baseline and Week 52 Earned Value Check for Calder Rapids
[Student Name]
Southern New Hampshire University
QSO 640: Project Management
Cost and Earned Value Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Below Plan and Still in Trouble: The Cost Baseline and Week 52 Earned Value Check for Calder Rapids
Introduction
The Calder Rapids LED streetlight conversion has a project budget of $12.6 million. This paper does two things. First, it sets the cost baseline, the time-phased budget against which performance will be measured, and sizes the reserves. Second, it applies earned value analysis at week 52, the first full status review after installation began, to judge how far the conversion has drifted, project its final cost and finish, and propose fixes.
Cost Baseline
Costs were estimated bottom-up for each of the 64 work packages and rolled up through the work breakdown structure. Installation is priced per light under the installer's contract, fixtures and nodes per unit under the supply contract, and internal labor from staff hours at loaded rates. The bottom-up figures shift a little money between lines compared with the charter's rough split, mainly toward project management and the third crew added in Module 5, but the total stays within the charter's envelope.
Cost baseline by WBS element
| WBS element | Cost |
|---|---|
| Project management, design, inventory and pilot | $0.62 million |
| Utility purchase | $2.10 million |
| Fixtures and control nodes | $6.40 million |
| Installation, including third crew | $2.20 million |
| Control system, training and handover | $0.28 million |
| Cost baseline (budget at completion) | $11.60 million |
| Contingency reserve | $1.00 million |
| Project budget | $12.60 million |
The Module 5 schedule tells finance which week each package's dollars fall in, so reading the curve at any week shows how much work, priced at budget, ought to be done by that date. Spending is light for the first 25 weeks and heavy from week 41, when fixtures arrive and installation of the utility-acquired lights begins.
Sizing the Contingency
The $1.0 million contingency reserve was sized from the risks identified so far, each estimated as probability times cost impact: a fixture price increase before the main order (about $280,000 expected), lower installation productivity than assumed (about $240,000), more failed poles needing wiring repairs than the 5 percent assumed (about $190,000), a higher utility purchase price (about $150,000) and smaller items totaling about $140,000. Flyvbjerg et al. (2002) gathered bridges, tunnels, roads and rail lines from several continents and decades, 258 in all, and saw the approval-stage budgets miss low so regularly that honest mistakes alone could not account for the pattern. Their warning applies to a city project whose estimate came partly from a vendor eager to win the work, which is why the reserve was built from named risks and why the steering group was told in advance that it might not be enough.
Status at Week 52
At week 52 the project had completed the inventory, design standards, pilot, installer award, utility purchase and fixture order, and installers had converted 3,900 lights, including all of District 1 and most of Districts 2 and 3. The finance office reported that spending of $5.9 million was below the $6.2 million planned by week 52 and concluded that the project was in good shape. Earned value analysis gives a different picture.
Earned value at week 52
| Week 52 item | Calder Rapids figure |
|---|---|
| Work scheduled by now, at budget (PV) | $6.20 million |
| Work finished by now, at budget (EV) | $5.40 million |
| Money spent so far (AC) | $5.90 million |
| CV: earned less spent | -$0.50 million |
| SV: earned less scheduled | -$0.80 million |
| CPI: earned per dollar spent | 0.92 |
| SPI: earned per dollar scheduled | 0.87 |
Spending was below plan because less work had been done than planned, not because work was cheaper. For each dollar spent, the project earned about 92 cents of planned work, and it had completed about 87 percent of the work scheduled by this date.
Forecasts
Two forecasts frame the likely final bill for Calder Rapids. Suppose the crews keep converting lights at the same 92 cents of planned work per dollar: then $11.6 million of planned work will take about $11.6 million over 0.915, close to $12.7 million. Suppose instead that the lateness also keeps pushing cost up, as overtime and remobilization often do: the $6.2 million of work still to be earned is then divided by about 0.80, the two indexes multiplied together, and added to the $5.9 million already spent, giving roughly $13.7 million. Christensen and Payne (1992) examined defense contracts and found that the cumulative cost index tended to settle early, changing little after a contract was about 20 percent complete, which suggests that the first forecast should not be treated as a worst case. At 47 percent complete by value, Calder Rapids is well past that point.
Predicting the finish is trickier. A dollar-based SPI drifts back toward 1.0 as the last lights go up, since every planned dollar is eventually earned, so on a project that ends months late it still reads perfect in the final week. Earned schedule sidesteps the problem by reading the baseline curve sideways: on the Calder Rapids plan, $5.4 million of work was due by week 46. Fifty-two weeks have passed and only 46 weeks' worth of planned work is done, which gives a time-based index of about 0.88. Dividing the planned 75-week duration by 0.88 forecasts a finish near week 85. Vanhoucke and Vandevoorde (2007) ran thousands of simulated project networks through the competing duration formulas, and the time-based earned schedule approach came out ahead in most network shapes and at most stages of completion. The forecast says the three-week buffer is already gone and the 78-week commitment is at risk by about seven weeks.
Causes of the Variances
Three causes account for most of the gap. Resident objections to the first fixtures' color stretched the pilot by three weeks, which pushed back the fixture order and every critical activity behind it. The fixture and node price rose about 7 percent between the estimate and the order because of a tariff on imported components, adding about $330,000, roughly a third of the contingency. Installation crews have converted about 19 lights a day instead of the 24 assumed, because older neighborhoods have more corroded connections and the installer's new crew members are still learning the control nodes.
Corrective Actions
The project manager recommends three actions. First, add a fourth installation crew from May through September, when daylight is longest, at about $180,000; together with a productivity target of 22 lights a day as crews gain experience, this is expected to recover five to six weeks. Second, trigger the air freight contingency for the next fixture lot, recovering about two weeks for $60,000. Third, renegotiate the node price, since the supplier's contract allows a review if volumes exceed 15,000 units, which they will. The added costs come from the contingency reserve, which would then stand at about $0.4 million against remaining risks. Because the cost-only forecast of $12.7 million already exceeds the $12.6 million project budget, the sponsor should brief the council now that a modest increase or a scope trade, such as deferring the control system's advanced features, may be needed. Reporting this at 47 percent complete gives the council choices it would not have at 90 percent.
Conclusion
The Calder Rapids cost baseline of $11.6 million and contingency of $1.0 million were built from the work and from named risks. At week 52, spending below plan concealed a project that was 13 percent behind schedule and 8 percent over cost for the work done. Earned value and earned schedule forecasts put the final cost between $12.7 and $13.7 million and the finish near week 85. Corrective actions aimed at the causes, a fourth crew, air freight and a node price review, can recover most of the time, and an early council briefing protects the project's credibility.
References
Christensen, D. S., & Payne, K. (1992). Cost performance index stability: Fact or fiction? Journal of Parametrics, 12(1), 27-40. https://doi.org/10.1080/10157891.1992.10462509
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002). Underestimating costs in public works projects: Error or lie? Journal of the American Planning Association, 68(3), 279-295. https://doi.org/10.1080/01944360208976273
Vanhoucke, M., & Vandevoorde, S. (2007). A simulation and evaluation of earned value metrics to forecast the project duration. Journal of the Operational Research Society, 58(10), 1361-1374. https://doi.org/10.1057/palgrave.jors.2602296
What the QSO 640 Module 6 instructions ask for
The Module 6 assignment in QSO 640 typically asks students to develop a project budget and apply earned value management to evaluate performance. Expect to price each work package, spread those costs across the calendar to form a baseline, set contingency and management reserves, then calculate planned value, earned value and actual cost at a status date, the cost and schedule variances, the cost and schedule performance indexes and forecasts such as estimate at completion. Strong papers explain how reserves were sized rather than picking a percentage, show every calculation, use more than one forecasting method and explain the difference, interpret what the indexes mean in plain terms, trace variances to causes and recommend actions with their expected effect. Some instructors also welcome earned schedule for forecasting the finish date.
How this QSO 640 Module 6 cost and earned value assignment example is built
The assignment sets the cost baseline for the LED streetlight conversion in Calder Rapids, a fictional Iowa city, at $11.6 million spread by week, with a $1.0 million contingency sized from named risks. At week 52, planned value is $6.2 million, earned value $5.4 million and actual cost $5.9 million: a cost performance index of about 0.92 and a schedule performance index of about 0.87. Forecasts put final cost between about $12.7 million and $13.7 million, and earned schedule projects a finish near week 85 against a plan of 75 and a commitment of 78. Causes are traced to the pilot extension, a fixture price rise and slow crews, and corrective actions are proposed. Flyvbjerg and colleagues, Christensen and Payne and Vanhoucke and Vandevoorde are cited.
Where the QSO 640 Module 6 rubric puts the points
The QSO 640 cost assignment generally rewards a baseline built from the work breakdown, reserves sized from identified risks, correct earned value calculations, clear interpretation of variances and indexes, forecasts made with more than one method and compared, variances traced to specific causes, corrective actions with their expected effect and research used to judge the forecasts. Papers stand out when they show that a project under budget on paper is in trouble. They lose marks for arithmetic errors, for confusing planned value with budget at completion, for reading a positive spending variance as good news, for a single forecast presented as certain or for recommendations unconnected to the causes found. Tables, APA references and plain writing complete the grade.
QSO 640 Module 6 help: the mistakes that cost points
Build the budget from the work packages, then spread it over time so you know what should have been spent by any week. Size reserves from your risk list, not a rule of thumb. At the status date you need three numbers: what you planned to have done (planned value), what you actually got done, valued at its budget (earned value), and what you spent (actual cost). Variances are differences; indexes are ratios. A cost index below one means each dollar buys less work than planned. Forecast the final cost at least two ways and explain why they differ. Then find the causes and act on them. A common mistake is comparing actual cost with planned value, which tells you nothing about whether the work got done.
Get QSO 640 Module 6 written to your instructions
Share the QSO 640 Module 6 instructions and your budget and progress figures. A writer prices the work into a time-phased baseline with reserves, runs the status-date numbers and indexes, projects the final bill and end date two different ways, traces the variances to causes, recommends corrective action and supports the analysis with project cost research. The first QSO 640 assignment is free and usually finished inside two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 640 papers and related MS Project Management samples
- QSO 640 Module 1 Discussion: Why the Conversion Is a Project
- QSO 640 Module 2 Project Charter Assignment: The Charter for 16,400 Lights
- QSO 640 Module 3 Scope Assignment: What Is In, What Is Out and the Work Breakdown
- QSO 640 Module 4 Discussion: Residents Who Found the Lights Too Blue
- QSO 640 Module 5 Schedule Assignment: The Network and Its Critical Path
- QSO 640 Module 7 Discussion: Fixtures That Failed After Installation
- QSO 640 Module 8 Risk Management Assignment: The Risk Register
- QSO 640 Module 9 Final Project: The Project Management Plan
- QSO 640 Module 10 Discussion: Closing the Project and Its Lessons
- QSO 530 Module 4 Confidence Interval Assignment: What Members Think, Within a Margin
- MKT 645 Module 7 Discussion: Display Advertising and Measuring Its Effect
- OL 665 Module 8 Journal: Interview With a Board Member
- ACC 550 Module 6 Joint Cost Assignment: Halves, Pieces, Meal and Shells From One Pound
QSO 640 Module 6 questions, answered
Where can I find a free QSO 640 Module 6 earned value sample?
The full QSO 640 Module 6 assignment is on this page: a cost baseline and week 52 earned value check for an invented city's streetlight project.
What is earned value in project management?
The budget attached to whatever work is truly finished on the status date; set beside the plan and the money spent, it shows whether a project is late, overspent or both.
How is the cost performance index calculated?
Earned value divided by actual cost; a value below 1.0 means the project is getting less work for each dollar spent than planned.
What is estimate at completion?
A forecast of the project's total cost, often budget at completion divided by the cost performance index, or a version that also accounts for schedule performance.
What is earned schedule?
A method that finds the time at which the planned value equaled the current earned value, giving schedule measures in time units that stay meaningful late in a project.