Project Management Plan, Revision 2: Calder Rapids LED Streetlight Conversion
[Student Name]
Southern New Hampshire University
QSO 640: Project Management
Final Project
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Project Management Plan, Revision 2: Calder Rapids LED Streetlight Conversion
Introduction
This is the second revision of the project management plan for the Calder Rapids LED streetlight conversion. The first was approved at week 20, after the scope statement, schedule and budget were complete. Since then the project has met three tests that the original plan did not anticipate well: residents objected to the color of the pilot fixtures, the week 52 earned value check found the work running late and costing more than its budgeted value, and control nodes failed in the first district. This revision keeps the project's purpose and scope, re-baselines the schedule with the sponsor's and the state's approval, and revises the quality, resource, communication and risk plans so that the document describes how the project is actually being run.
Project Summary
The city is swapping every one of its 16,400 street lamps for networked LED units, among them the 11,200 poles bought from the power company and the acorn-style lamps along Riverside's old blocks. Money comes from three places, borrowed, rebated and granted, and totals $12.6 million. Its objectives remain those in the charter: every light converted and reporting, spending within budget, operating cost at least 55 percent lower in the first full year, 90 percent of outages repaired within 48 hours and fewer than one complaint per 1,000 lights a month. The completion objective has changed from 78 to 82 weeks, as explained below. Pinto and Slevin (1987) found that experienced managers rated a clearly defined mission and support from top management first among the factors in project success; the steering group's decision to keep the objectives unchanged, apart from the date, is meant to keep that clarity.
Scope Management
Nothing in the scope baseline has moved: the same eight deliverables, each with its test, and the same breakdown into work packages. Two scope decisions since the first revision are recorded. The Ward 2 request for 140 new lights was declined and referred to next year's capital budget. The color temperature decision after the pilot, 3000 kelvin citywide and 2700 kelvin in the historic district with dimming after midnight, was approved as a change to the design standard without changing cost. A scope trade is now held in reserve: deferring the control system's advanced reporting module, worth about $110,000, which the sponsor may approve if the contingency falls below $200,000.
Schedule Management
The original baseline planned completion at week 75 with a three-week buffer to week 78. At week 52, earned schedule analysis forecast a finish near week 85. The approved recovery measures, an extra summer crew and faster shipping of the coming fixtures, should win back about three weeks. Rather than keep a baseline the project can no longer meet, the sponsor approved a new baseline finishing at week 80 with a two-week buffer to week 82, and the state energy office granted a written extension of the grant deadline to the end of January. The critical path now runs through installation of the utility-acquired lights, control system commissioning and handover. Buffer consumption will be reported monthly.
Cost Management
The cost baseline remains $11.6 million. The contingency reserve stands at about $400,000 after funding the corrective actions. After the node price review and the corrective actions, the forecast at completion using the cost index alone is about $12.6 million, at the limit of the project budget. The project will report three forecasts at each steering meeting: the cost-index forecast, a forecast that also accounts for schedule performance, and a range. Lipke et al. (2009) showed how statistical methods can be applied to earned value and earned schedule data to place confidence limits around forecasts of final cost and duration, which helps a sponsor see how much a forecast can be trusted rather than reading one number as certain. The finance office has agreed that variances will be reported as earned value results, ending the earlier practice of comparing spending with the plan alone.
Quality Management
The original quality plan relied on acceptance testing of each district. The revised plan adds prevention at the pole, based on the node failures in District 1.
Quality activities
| Activity | When | Responsible | Standard |
|---|---|---|---|
| Photo of seated gasket and node in installer app | Every pole | Installer crew | Required before light is marked installed |
| First-pole check | Each crew, each morning | Crew lead | Checklist signed in app |
| Light-level measurement | 10% of streets per district | City traffic engineer | Design standard by street type |
| Seven-day reporting test | Each district | Lighting supervisor | All nodes report without fault |
| Supplier batch test | Each node shipment | Quality lead | Under 1% failures on sample of 50 |
| Quality review | Monthly | Project manager | Failure rates, rework cost, causes |
Productivity is now measured in lights accepted rather than lights installed, so that the schedule pressure from the corrective actions does not push crews to skip the gasket step.
Resource Management
The installer provides four crews of two through September and three thereafter. City staff on the project include the project manager, a traffic engineer at half time, the lighting supervisor at one-quarter time, a quality lead from public works, an energy manager, a communications officer and a finance analyst for monthly reporting.
Responsibility chart for main deliverables (R responsible, A accountable, C consulted, I informed)
| Deliverable | Project manager | Installer | Lighting supervisor | IT | Sponsor |
|---|---|---|---|---|---|
| District conversions | A | R | C | I | I |
| Historic district | A | R | C | I | C |
| Control system | A | C | C | R | I |
| Training and handover | A | C | R | C | I |
| Change approvals over $50,000 | R | I | I | I | A |
Communication Management
The communication plan was rebuilt after the pilot showed that residents are several groups with real influence.
Communication plan by stakeholder group
| Stakeholder | Information | Channel | Frequency | Owner |
|---|---|---|---|---|
| City Council | Progress, cost forecast, risks, decisions needed | Written report and briefing | Monthly | Sponsor |
| Steering group | Earned value, buffer, risk register, changes | Meeting with one-page dashboard | Monthly | Project manager |
| Residents of district about to convert | Dates, what will change, dimming, how to comment | Door hangers, neighborhood open house, city website | Three weeks before work | Communications officer |
| Neighborhood associations and dark-sky group | Design decisions, complaint data | Meeting | Quarterly | Project manager |
| Police department | Arterial light levels, outage data | Email report | Monthly | Traffic engineer |
| Installer | Schedule, quality results, issues | Site meeting | Weekly | Project manager |
| State energy office | Progress against grant terms | Written report | Quarterly | Finance analyst |
Risk Management
At week 56 the register holds ten entries, eight threats and two pieces of possible good news, and none lacks a named owner, a warning sign to watch and an agreed reply. Expected cost of threats after responses is about $380,000 against about $400,000 of contingency. Zwikael and Ahn (2011) surveyed hundreds of project managers in three countries and found that even moderate risk planning was enough to weaken the link between high risk and poor project results, which supports the plan's approach: a short register reviewed monthly by its owners rather than elaborate modeling. Each monthly steering session walks the list line by line, with the remaining reserve printed on the same sheet.
Procurement Management
The project has three main contracts. The utility purchase agreement, signed at week 22, transferred the lights at a fixed price and placed the risk of hidden wiring defects on the city, which is why that risk is in the register. The fixture and node supply contract sets unit prices with a volume clause above 15,000 units and a warranty that covers replacement and labor for batch defects, transferring that risk to the supplier. The installer contract pays a unit price per light accepted, not installed, since the revision, which places the cost of rework on the installer, plus a per-light incentive above 22 lights per crew per day. Contract changes follow the change control process.
Change Control
Change requests are submitted on the project form and assessed by the project manager within five working days for effect on scope, schedule, cost, quality and risk. Small changes, under $50,000 and two weeks, stop at the project manager's desk; bigger ones need the steering group; changes to the total budget or the completion objective go to the council. Approved changes update this plan, and the change log is reported monthly.
Closing
The project will close when the control system is commissioned, the lighting crew has passed its training test and the last district has met acceptance. Closing includes a punch list walk with the installer, final payment held until all items are cleared, warranty documentation transferred to public works, the final financial report to the council and the state, archiving of records and a lessons-learned review with the steering group, the installer and the lighting crew. Operating cost and reliability objectives will be measured for one year after closing and reported by public works.
Conclusion
The second revision of the Calder Rapids plan keeps the project's purpose and scope and is honest about its date: a re-baselined 80-week schedule with a buffer to 82 weeks, a cost baseline protected by a thin but analyzed reserve and a scope trade held ready. Quality now starts at the pole, communication treats residents as groups with influence, contracts place risks where they can best be managed, and every risk and quality action has an owner. A sponsor could run the rest of the project from this document, which is the test a plan has to pass.
References
Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27(4), 400-407. https://doi.org/10.1016/j.ijproman.2008.02.009
Pinto, J. K., & Slevin, D. P. (1987). Critical factors in successful project implementation. IEEE Transactions on Engineering Management, EM-34(1), 22-27. https://doi.org/10.1109/TEM.1987.6498856
Zwikael, O., & Ahn, M. (2011). The effectiveness of risk management: An analysis of project risk planning across industries and countries. Risk Analysis, 31(1), 25-37. https://doi.org/10.1111/j.1539-6924.2010.01470.x
What the QSO 640 Module 9 instructions ask for
The QSO 640 final project generally asks students to develop a comprehensive project management plan for a case or a project of their own. Expect to bring together the charter and the subsidiary plans for scope, schedule, cost, quality, resources, communications, risk and procurement, along with change control and closing. Strong plans hang together so that no section contradicts another: the schedule matches the work breakdown, the budget matches the schedule, reserves match the risk analysis, the communication plan names the stakeholders identified earlier, and quality and risk responses appear as tasks with owners. Instructors also value plans that show judgment, explaining why a baseline was set where it was and how the plan will be kept current as the project changes.
How this QSO 640 Module 9 final project example is built
The project presents the management plan for the LED streetlight conversion in Calder Rapids, a fictional Iowa city replacing 16,400 lights for $12.6 million, as revised at week 56. It summarizes the charter and a scope baseline of eight deliverables, re-baselines the schedule to an 82-week finish backed by a state grant extension, keeps the $11.6 million cost baseline with about $400,000 of contingency and a $110,000 scope trade held ready, and sets out quality, resource, communication, risk, procurement, change control and closing plans. Each section notes what changed after the pilot complaints, the week 52 earned value check and the failing control nodes. Pinto and Slevin, Zwikael and Ahn and Lipke and colleagues are cited.
Where the QSO 640 Module 9 rubric puts the points
Marks on the QSO 640 final project typically go to a complete plan covering every required area, consistency across sections, baselines that follow from the work breakdown and schedule, reserves tied to risk, quality and risk actions with owners, a communication plan matched to stakeholders, procurement choices that share risk sensibly, a working change control process, a closing plan and evidence of judgment in the reasoning. Plans score well when a reader could run the project from them. They lose points for sections copied from milestones without reconciling them, for figures that disagree between sections, for generic communication or quality plans and for ignoring what the earlier analyses found. Tables, APA references and professional formatting complete the grade.
QSO 640 Module 9 help: the mistakes that cost points
Start by listing the baselines your plan will hold: scope, schedule and cost. Make sure they agree, because instructors notice when the schedule says 75 weeks and the budget is spread over 78. Then add the subsidiary plans, each short and specific: who does quality checks and when, who needs what information how often, which risks have money set aside, which contracts carry which risks. Show how a change gets approved and how the project will close. Where your milestones taught you something, revise the plan and say so. Read the whole plan once as a sponsor would and look for contradictions. Final projects often paste milestones together unchanged; the strongest ones reconcile them into a single, current plan.
Get QSO 640 Module 9 written to your instructions
Share the QSO 640 final project guidelines, milestone feedback and your case or project. A writer assembles an integrated plan covering scope, schedule, cost, quality, resources, communications, risk, procurement, change control and closing, keeps every section consistent with the others, explains the reasoning behind baselines and reserves and draws on project management research. We draft your first QSO 640 project without charge, in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 640 papers and related MS Project Management samples
- QSO 640 Module 1 Discussion: Why the Conversion Is a Project
- QSO 640 Module 2 Project Charter Assignment: The Charter for 16,400 Lights
- QSO 640 Module 3 Scope Assignment: What Is In, What Is Out and the Work Breakdown
- QSO 640 Module 4 Discussion: Residents Who Found the Lights Too Blue
- QSO 640 Module 5 Schedule Assignment: The Network and Its Critical Path
- QSO 640 Module 6 Cost and Earned Value Assignment: The Budget and the Week 52 Check
- QSO 640 Module 7 Discussion: Fixtures That Failed After Installation
- QSO 640 Module 8 Risk Management Assignment: The Risk Register
- QSO 640 Module 10 Discussion: Closing the Project and Its Lessons
- MKT 610 Module 4 Discussion: Choosing a Message Appeal
- BMB 655 Module 8 Budgeting Assignment: A Cash Budget Built Around Late Royalty Statements
- ACC 610 Module 6 Milestone Two: Impairment of a Service Center and of Goodwill
- QSO 600 Module 9 Final Project: The Operations Improvement Plan
QSO 640 Module 9 questions, answered
Where can I find a free QSO 640 Module 9 Final Project sample?
The full QSO 640 Module 9 final project is on this page: a revised project management plan for an invented city's LED streetlight conversion.
What is in a project management plan?
The baselines for scope, schedule and cost plus subsidiary plans for quality, resources, communications, risk, procurement, change control and closing.
What does re-baselining a project mean?
Formally approving a new schedule or cost baseline after a change too large to manage within reserves, so performance is measured against a realistic plan.
Why must sections of a project plan agree with each other?
Because the schedule, budget, risks and resources depend on one another, and contradictions mean the plan cannot be followed or measured.
How often should a project management plan be updated?
Whenever an approved change alters a baseline or a subsidiary plan, and at least at each major review, so it reflects the project as it is.