Four Hundred Thousand Dollars Left: The Calder Rapids Risk Register at Week 56
[Student Name]
Southern New Hampshire University
QSO 640: Project Management
Risk Management Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Four Hundred Thousand Dollars Left: The Calder Rapids Risk Register at Week 56
Introduction
The earned value check at week 52 of the Calder Rapids LED streetlight conversion forecast a final cost above the $12.6 million budget and a finish several weeks past the 78-week commitment. The corrective actions approved by the sponsor, a fourth installation crew and air freight for the next fixture lot, drew on the contingency reserve, leaving about $400,000. The register prepared during planning was built for a project with $1.0 million of reserve and a three-week schedule buffer, neither of which still exists. This paper updates the register at week 56, quantifies the largest risks, sets responses and compares the remaining risk with the remaining reserve.
Method
The Calder Rapids threats were gathered one afternoon at the public works yard, where the team sat with the installer's lead, the lighting supervisor and an analyst from finance, using the work breakdown structure as a checklist so that each deliverable was examined. Every entry names its source condition, the uncertain event and the consequence for cost or dates. Probability and impact are rated from 1 to 5, and the largest risks are then estimated in dollars and weeks. Raz and Michael (2001) surveyed project managers in software and high-technology firms in Israel about the risk management tools they used and found that firms making more use of such tools tended to report better project management performance, with simple tools such as ranking and assigning responsibility among the more valuable. The register therefore emphasizes clear ownership over elaborate modeling.
The Register
Calder Rapids risk register, week 56 (P and I rated 1 to 5)
| Ref | What could happen and why | Likelihood | Impact | P x I | Owner | Warning sign | Planned reply |
|---|---|---|---|---|---|---|---|
| T1 | Tariff on imported node parts may rise before the last fixture lot ships, adding cost | 3 | 4 | 12 | Purchasing manager | Federal notice of tariff review | Mitigate: buy last lot early under contract option |
| T2 | State grant requires completion by December; a slip past it loses grant funds | 2 | 5 | 10 | Project manager | Forecast finish after November 15 | Mitigate: grant districts first; written extension request now |
| T3 | Older neighborhoods' wiring may have more corroded connections than assumed, adding repair cost | 4 | 2 | 8 | Lighting supervisor | Repair rate over 6% in any district | Accept with reserve; track by district |
| T4 | Installer crews may stay below 22 lights a day, adding weeks and cost | 3 | 3 | 9 | Installer's project manager | Weekly rate under 20 for two weeks | Mitigate: per-light incentive above 22 |
| T5 | Winter weather may stop arterial work if installation runs past mid-November | 2 | 4 | 8 | Project manager | Forecast arterial finish after November 1 | Mitigate: resequence arterials before residential streets |
| T6 | IT security review of the control system may find gaps, delaying commissioning | 2 | 3 | 6 | Chief information officer | Review findings rated high | Mitigate: start review now, not at commissioning |
| T7 | Node supplier firmware defect may recur in new batches, causing failures | 2 | 2 | 4 | Quality lead | Any batch failure over 1% | Transfer: warranty replacement and labor credit |
| T8 | Residents in later districts may object to light levels or dimming | 2 | 2 | 4 | Communications officer | 311 complaints over 3 per 1,000 lights | Accept: open house per district; adjust dimming |
| O1 | Utility may pay added rebate if dimming schedules are verified by year end | 3 | 3 | 9 | Energy manager | Utility program notice | Exploit: verify District 1 to 3 dimming in October |
| O2 | Node supplier's volume clause may lower unit price above 15,000 units | 4 | 2 | 8 | Purchasing manager | Order total passes 15,000 | Exploit: invoke clause at next order |
The scores separate a few risks that need money or action now from several that only need watching. T1 and T2 rank highest and are analyzed below. T3, T4 and T5 are moderate and have clear triggers, so their owners can act before they grow.
Quantifying the Largest Risks
Expected value of the main threats before and after response
| Risk | Probability | Impact | Expected value before | Response cost | Probability after | Expected value after |
|---|---|---|---|---|---|---|
| T1 Tariff increase | 30% | $420,000 | $126,000 | $35,000 (early purchase, storage) | 5% | $21,000 |
| T2 Grant deadline missed | 15% | $1,200,000 | $180,000 | $5,000 (staff time) | 6% | $72,000 |
| T3 Wiring faults above assumption | 50% | $190,000 | $95,000 | none | 50% | $95,000 |
| T4 Installer productivity | 40% | $140,000 | $56,000 | $40,000 (incentive) | 20% | $28,000 |
| T5 Winter stoppage | 25% | $260,000 | $65,000 | none (resequencing) | 10% | $26,000 |
| Other threats (T6 to T8) | $48,000 | $10,000 | $33,000 | |||
| Total | $570,000 | $90,000 | $275,000 |
For T1, buying the last fixture lot early costs about $35,000 in storage and earlier payment but cuts the chance of paying the higher tariff from 30 to about 5 percent, lowering expected cost by more than $100,000. For T2, the response is cheap: the grant agreement allows extensions requested in writing before the deadline, and the districts the grant counts are being converted first. Kutsch and Hall (2010) studied why project managers in information technology projects sometimes left known risks unaddressed and found that some risks were set aside deliberately, because acknowledging them seemed politically awkward or not worth the effort. The grant risk is exactly that kind: nobody wanted to tell the state early that the project was late. Putting it in the register turned the awkward letter to the state into an assignment for the project manager, due on the last Friday of the month.
Reserve Compared With Risk
After responses, the expected value of remaining threats is about $275,000, and the responses themselves cost about $90,000, for a total of about $365,000, plus roughly $15,000 for small risks not quantified, or about $380,000. The remaining reserve is about $400,000. The margin is thin. Expected value is an average; if T3 and T4 both occur at full impact, they alone would use $330,000.
Hillson (2002) argues that the same risk process should be used to manage opportunities, with responses that try to make them happen or enlarge them. Two opportunities help here. The utility's efficiency program pays an added rebate of about $150,000 if dimming schedules are verified before year end, which the energy manager judges about 50 percent likely, worth about $75,000 in expected value, and the supplier's volume clause could lower node prices by about $60,000. Neither is counted in the reserve, but both are being pursued.
Recommendation
The project does not need to ask the council for more money now, but it should not pretend the margin is comfortable. The project manager recommends that the sponsor approve the early fixture purchase and the installer incentive, that the grant extension request be sent this month and that the register be reviewed at every monthly steering meeting rather than quarterly. If the reserve falls below $200,000 while T3 or T4 is still active, the sponsor should brief the council on options, including deferring the control system's advanced reporting features.
Monitoring
Each owner reports on triggers weekly in the project status meeting. Risks are closed when the event can no longer happen, such as T1 once the last lot is delivered. New risks are added as districts begin. The register, the reserve balance and the earned value indexes appear on the same page of the steering group report, so that risk, cost and schedule are read together.
Conclusion
With $400,000 of reserve left, Calder Rapids cannot cover every risk with money. The updated register spends on the two responses that buy the most risk reduction per dollar, turns the most uncomfortable risk into a letter with a deadline, accepts the wiring and weather risks with clear triggers and pursues two opportunities. Expected risk after responses comes close to the reserve, which is why monthly review, not a larger request, is the right next step.
References
Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, 20(3), 235-240. https://doi.org/10.1016/S0263-7863(01)00074-6
Kutsch, E., & Hall, M. (2010). Deliberate ignorance in project risk management. International Journal of Project Management, 28(3), 245-255. https://doi.org/10.1016/j.ijproman.2009.05.003
Raz, T., & Michael, E. (2001). Use and benefits of tools for project risk management. International Journal of Project Management, 19(1), 9-17. https://doi.org/10.1016/S0263-7863(99)00036-8
What the QSO 640 Module 8 instructions ask for
The QSO 640 Module 8 assignment usually asks students to develop a risk management plan or risk register for a project. Expect to identify risks, analyze their probability and impact qualitatively and, for the most important, quantitatively, plan responses such as avoiding, transferring, mitigating or accepting, assign owners and define triggers that show when a risk is becoming real. Strong papers spell out what triggers each risk, what might happen and what it would do to the project, rather than naming a vague worry, include opportunities as well as threats, size responses against the risk they address, compare the expected cost of the remaining risks with the reserve available and explain how the register will be kept current. A register that ranks every risk as high tells the reader nothing, so good papers make choices.
How this QSO 640 Module 8 risk management assignment example is built
The assignment updates the risk register for the LED streetlight conversion in Calder Rapids, a fictional Iowa city, after the week 52 check left about $0.4 million of contingency. Eight threats and two opportunities are scored, with owners, triggers and responses. The largest are quantified: a tariff increase before the last fixture lot, 30 percent likely at $420,000, cut by buying early under a contract option; missing the state grant deadline, 15 percent likely at $1.2 million, addressed by finishing grant-eligible districts first and asking for an extension now. Threats after responses total about $380,000 in expected value against $400,000 of reserve, plus a rebate opportunity worth about $75,000. Raz and Michael, Hillson and Kutsch and Hall are cited.
Where the QSO 640 Module 8 rubric puts the points
Grading in the QSO 640 risk assignment generally rewards risks stated precisely, sensible probability and impact ratings, quantified analysis of the largest risks, responses that fit each risk and are worth their cost, named owners and triggers, attention to opportunities, a comparison of expected risk with available reserves and a plan for monitoring. Papers stand out when the register changes a decision. They lose credit for generic risks that could belong to any project, for responses that cost more than the risk, for registers with no owners, for ignoring opportunities or for a reserve figure unconnected to the risks. The last points ride on legible tables, sound APA entries and plain sentences.
QSO 640 Module 8 help: the mistakes that cost points
Write each risk as "because of this cause, this event may happen, which would cause this effect," so you know what to watch and what to change. Score probability and impact on a simple scale and rank them. For the top few, estimate probability as a percentage and impact in dollars or weeks, and multiply to get expected value. Choose a response for each: avoid, transfer, reduce or accept, and estimate what the response costs and how much it lowers the risk. Give each an owner and a trigger. Add any opportunities, since good news can be managed too. Compare the total expected value of remaining risks with your reserve. Papers often stop at the list; the useful part is the comparison that tells the sponsor whether the reserve is enough.
Get QSO 640 Module 8 written to your instructions
Share the QSO 640 Module 8 instructions and your project's situation. A writer identifies threats and opportunities, scores probability and impact, assigns owners, triggers and responses, quantifies the largest risks by expected value, compares the total with the reserve and sets a review routine, citing project risk research. The first QSO 640 assignment is free and comes back within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 640 papers and related MS Project Management samples
- QSO 640 Module 1 Discussion: Why the Conversion Is a Project
- QSO 640 Module 2 Project Charter Assignment: The Charter for 16,400 Lights
- QSO 640 Module 3 Scope Assignment: What Is In, What Is Out and the Work Breakdown
- QSO 640 Module 4 Discussion: Residents Who Found the Lights Too Blue
- QSO 640 Module 5 Schedule Assignment: The Network and Its Critical Path
- QSO 640 Module 6 Cost and Earned Value Assignment: The Budget and the Week 52 Check
- QSO 640 Module 7 Discussion: Fixtures That Failed After Installation
- QSO 640 Module 9 Final Project: The Project Management Plan
- QSO 640 Module 10 Discussion: Closing the Project and Its Lessons
- ACC 693 Module 9 Milestone Three: The Timeline and the Findings
- ACC 550 Module 9 Transfer Pricing Assignment: What Should Candy Pay for Halves?
- MGT 600 Module 7 Performance Metrics Assignment: What to Measure at Each Branch
- ACC 645 Module 7 Discussion: Assurance on Emissions Data
QSO 640 Module 8 questions, answered
Where can I find a free QSO 640 Module 8 risk register sample?
The complete QSO 640 Module 8 assignment is on this page: a scored and quantified risk register for an invented city's streetlight project.
What is a risk register?
A document listing each project risk with its cause, probability, impact, owner, trigger, planned response and current status.
What is expected monetary value in risk analysis?
Chance times dollar consequence: a 30 percent shot at a $420,000 hit is worth $126,000, a figure that lets risks be ranked and reserves sized.
What are the four responses to project threats?
Avoid the risk, transfer it to another party, mitigate its probability or impact, or accept it and set aside a reserve.
Can a risk register include opportunities?
Yes. Opportunities are uncertain events with positive effects, managed by exploiting, sharing, enhancing or accepting them.