Free sample paper for QSO 345 Module 2
Project Charter: Relocation of Harrow Mutual Insurance Agency Headquarters
[Student Name]
Southern New Hampshire University
QSO 345: Project Management for CAPM Certification
Project Charter Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Project Charter: Relocation of Harrow Mutual Insurance Agency Headquarters
Purpose and Business Case
Harrow Mutual Insurance Agency leases three floors of a downtown Omaha office tower under a lease that ends on June 30, 2027. The landlord has declined to renew, because the floors are being converted to apartments. In September 2026 the agency purchased a 42,000-square-foot former printing plant in midtown for $4.2 million, a decision approved by the board as cheaper over 15 years than leasing comparable space and as an opportunity to bring all teams onto one floor. This project will renovate the building, equip it and move the agency's 140 employees and operations into it before the lease ends, without disrupting service to the agency's 21,000 clients.
Objectives and Success Criteria
The project will be considered successful if it meets five objectives. First, all employees will be working in the new building by Friday, June 25, 2027, leaving five days before the lease ends. Second, total project cost will not exceed $3.1 million. Third, telephone, email and agency management systems will be unavailable for no more than four business hours during the cutover. Fourth, no client files, paper or electronic, will be lost or misplaced, verified by an audit of 500 randomly chosen client records after the move. Fifth, at least 75 percent of employees will report being satisfied or very satisfied with the new workplace in a survey 60 days after the move.
High-Level Scope
In scope are architectural design and permits; demolition and abatement; renovation of the building into open offices, meeting rooms, a training room, a break room and a records room; network cabling, wireless, telephones and meeting room audio and video; furniture selection, purchase and installation; the physical move of people, files and equipment; staff preparation for the move; and return of the leased floors in the condition the lease requires.
Out of scope are changes to the agency management system or other insurance software, new hires or changes to team structures, landscaping beyond what the city requires for an occupancy permit and the sale or disposal of the agency's old furniture, which will be handled separately by facilities.
Constraints and Dependencies
Three constraints are fixed. The lease end of June 30, 2027, cannot move: the landlord's conversion contractor starts work on July 1, and the lease charges holdover rent at twice the current rate for any day past it. The $3.1 million budget is the board's approval, and any increase must return to the board. Client service must continue throughout, which means telephones and the agency management system may go down only on a weekend and only for the four hours set in the objectives. The project also depends on parties outside the agency. The city must approve the building permit and issue the certificate of occupancy; the internet provider must run fiber to an address it has never served; and the insurance carriers whose systems the agency uses must be told the new address before policies issued after June 1 show it. Each dependency has a named owner on the project team, and each will be tracked in the project plan from the first week rather than discovered during construction.
Deliverables and Milestones
Summary milestones
| Milestone | Target date |
|---|---|
| Charter approved | November 2, 2026 |
| Design complete and building permit issued | December 23, 2026 |
| Construction contract awarded | January 15, 2027 |
| Demolition and abatement complete | February 5, 2027 |
| Construction complete | April 30, 2027 |
| Technology and furniture installed | May 21, 2027 |
| Certificate of occupancy issued | May 28, 2027 |
| Move weekend complete | June 7, 2027 |
| Old floors returned and project closed | June 25, 2027 |
Summary Budget
Summary budget
| Category | Amount |
|---|---|
| Design, engineering and permits | $210,000 |
| Demolition and abatement | $140,000 |
| Construction | $1,550,000 |
| Technology and audio-visual | $360,000 |
| Furniture | $480,000 |
| Movers | $60,000 |
| Restoration of leased floors | $90,000 |
| Project management costs | $30,000 |
| Contingency | $180,000 |
| Total | $3,100,000 |
The contingency, about 6 percent of the total, is reserved for identified risks, chiefly unknown building conditions, and may be released by the project manager up to $25,000 per item; larger draws require the sponsor's approval.
Stakeholders
The sponsor is Dana Whitcomb, chief executive. Key stakeholders are the agency's board, which approved the purchase; the leadership team; all 140 employees, especially the 32 client service staff whose phones must keep working; the agency's clients and insurance carriers; the architect, general contractor, technology vendor, furniture dealer and movers; the City of Omaha permitting and inspection offices; and the downtown landlord.
Initial Risks and Assumptions
The main initial risks are hidden conditions in a 1960s building, such as asbestos or structural problems; delays in permits or inspections; long lead times for furniture and electrical equipment; and staff resistance to an open office. The charter assumes the contractor can begin by mid-January, the budget includes no change to insurance systems and the agency's internet provider can install service at the new address within 60 days of order.
Project Manager Authority
Pinto and Slevin (1987) found that clear mission and top management support head the list of factors managers see as critical to project success, and Zwikael and Smyrk (2015) argue that project governance must balance control by the funder with trust in the project manager. Accordingly, the project manager, the agency's operations manager, may assign team members from each department for up to eight hours a week, approve vendor change orders up to $25,000 within the budget, set meeting and reporting schedules and make decisions on layout within the approved design. Changes to objectives, scope, the total budget or the move date require the sponsor's approval. The project manager will report to the sponsor weekly and to the leadership team monthly.
Approach to Planning
Dvir et al. (2003) found that the effort put into defining requirements and specifications early was associated with project success. The first four weeks will therefore be spent gathering each team's space and technology requirements before the architect completes the drawings, and the detailed scope, work breakdown structure, schedule and budget will follow in the project plan.
Approval
Approved by Dana Whitcomb, Chief Executive Officer and Project Sponsor, and accepted by the Operations Manager as Project Manager, November 2, 2026.
References
Dvir, D., Raz, T., & Shenhar, A. J. (2003). An empirical analysis of the relationship between project planning and project success. International Journal of Project Management, 21(2), 89-95. https://doi.org/10.1016/S0263-7863(02)00012-1
Pinto, J. K., & Slevin, D. P. (1987). Critical factors in successful project implementation. IEEE Transactions on Engineering Management, EM-34(1), 22-27. https://doi.org/10.1109/TEM.1987.6498856
Zwikael, O., & Smyrk, J. (2015). Project governance: Balancing control and trust in dealing with risk. International Journal of Project Management, 33(4), 852-862. https://doi.org/10.1016/j.ijproman.2014.10.012
What the QSO 345 Module 2 instructions ask for
The QSO 345 Module 2 assignment usually asks students to write a project charter, the document that formally authorizes a project and gives the project manager authority to use resources. Expect to include the project's purpose or business case, measurable objectives and success criteria, a high-level description of scope and requirements, major deliverables and milestones, a summary budget, key stakeholders, high-level risks and assumptions, the project manager's name and authority and the sponsor's approval. Strong charters make objectives specific and measurable, state what is excluded as well as included, connect the project to a business need and keep detail at the right level, since the charter authorizes the project rather than planning it in full.
How this QSO 345 Module 2 project charter assignment example is built
The assignment drafts the charter for relocating Harrow Mutual Insurance Agency, a fictional agency of 140 employees in Omaha. The business case rests on the lease ending June 30, 2027, and on the purchase of a former printing plant. Five objectives are measurable: all staff working in the new building by June 25, total cost within $3.1 million, phone and system downtime of no more than four hours during the cutover, no lost client files and employee satisfaction with the new workplace of at least 75 percent. Scope includes renovation, technology, furniture and the move but excludes new hires and changes to insurance systems. Pinto and Slevin, Dvir, Raz and Shenhar and Zwikael and Smyrk on governance frame the document.
Where the QSO 345 Module 2 rubric puts the points
Grading for the QSO 345 charter assignment rests on a convincing business case, specific and measurable objectives, an appropriate high-level scope with exclusions, realistic milestones and budget, identification of key stakeholders and risks, a clear statement of the project manager's authority and sponsor approval and an appropriate level of detail. The strongest charters connect every objective to the business need and define success so that anyone could tell later whether the project achieved it. Credit drops when objectives are vague, scope has no boundaries, the budget lacks a contingency, the project manager's authority is missing or the charter tries to be a full project plan. Format, clarity and APA citations complete the rubric.
QSO 345 Module 2 help: the mistakes that cost points
Start with why the project exists: the business need or opportunity it serves. Then write three to six objectives in measurable form, each with a target and a date, such as finishing by a specific day within a specific budget. Describe scope in a few sentences and list what is excluded, since exclusions prevent arguments later. Add the major deliverables and milestones, a summary budget with a contingency, the main stakeholders, a short list of risks and assumptions and a statement of what the project manager may decide without asking the sponsor. A common mistake is writing objectives such as "a smooth move," which cannot be measured; another is filling the charter with detailed tasks that belong in the plan. End with a sponsor signature line.
Get QSO 345 Module 2 written to your instructions
Share the QSO 345 Module 2 instructions and describe the project you are chartering. A writer drafts the charter with business case, measurable objectives, high-level scope and exclusions, milestones, budget, stakeholders, initial risks and the project manager's authority, in the format project sponsors expect and CAPM questions test. Your first QSO 345 charter is free, and the draft arrives in roughly two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 345 papers and related BS Operations Management samples
- QSO 345 Module 1 Discussion: Why Moving an Office Is a Project
- QSO 345 Module 3 Project One: Scope, Work Breakdown and Schedule
- QSO 345 Module 4 Discussion: Mapping Who Can Stop the Move
- QSO 345 Module 5 Risk Register Assignment: What Could Keep 140 People From Moving
- QSO 345 Module 6 Discussion: Predictive, Agile or Both for an Office Move?
- QSO 345 Module 7 Project Two: Earned Value at Week 18
- QSO 345 Module 8 Discussion: A Furniture Vendor's Hockey Tickets
- MKT 455 Module 5 Milestone Two: Content Plan, Calendar and Creator Partners
- OL 211 Module 3 Milestone One: HR Needs Assessment
- ACC 318 Module 6 Discussion: A Covenant Breach and Where the Debt Goes
- HRM 225 Module 4 Discussion: Build or Buy Digital Talent?
QSO 345 Module 2 questions, answered
Where can I find a free QSO 345 Module 2 Project Charter Assignment sample?
The complete QSO 345 Module 2 assignment is on this page: a project charter for an invented insurance agency's headquarters relocation.
What is a project charter?
The document issued by the sponsor that formally authorizes a project, states its purpose, objectives and high-level scope and gives the project manager authority to apply resources.
What goes in a project charter?
Business case, measurable objectives and success criteria, high-level scope and requirements, milestones, summary budget, stakeholders, high-level risks and assumptions, the project manager's authority and approval.
Who signs the project charter?
The project sponsor or initiator, usually a senior manager who controls the funding and can authorize the project manager to use organizational resources.
How detailed should a project charter be?
Detailed enough to authorize the project and set its boundaries and success criteria, but not a full plan; detailed scope, schedules and budgets come later in planning.