QSO 345 Module 4 Discussion Example

Reviewed by Portia Lambrick, MBA

This QSO 345 Module 4 Discussion sample identifies and analyzes the stakeholders of one project and plans how to engage and communicate with each. SNHU QSO 345 (QSO-345) turns to stakeholder and communication management in Module 4 of its BS Operations Management course on project management for the CAPM exam. The project is the relocation of Harrow Mutual Insurance Agency, an invented Omaha agency, to a renovated building by June 30, 2027. The post sorts stakeholders by power and interest and by salience, shows that two outsiders could stop the move and sets out who hears what, how often and through which channel.

CourseQSO 345 Project Management for CAPM® Certification
ModuleModule 4
Paper typeundergraduate discussion post identifying and analyzing project stakeholders and planning how to engage and communicate with them
LengthAbout 410 words, 3 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 345 Module 4

1

Module Four Discussion

The Inspector and the Fiber Crew

My first stakeholder list for the Harrow Mutual move had eleven entries, and every one was inside the agency: the chief executive as sponsor, the leadership team, the board, IT, facilities, finance, human resources, the client service team, the sales teams, the records clerk and the employees generally. When I asked who could stop the move, though, the two clearest answers were not on it. The City of Omaha's building inspector will not issue a certificate of occupancy until fire protection, exits and accessibility pass, and without that certificate no one may work in the building. The internet provider must bring fiber into a building that has never had it, and without a live circuit our phones and agency system cannot run. A second pass added both, along with the downtown landlord, the general contractor, the furniture dealer, the movers, our insurance carriers and our 21,000 clients.

What this page is doingThe first list was too short.
2

On a power and interest grid, the sponsor, the leadership team and the client service staff are high in both and will be managed closely. The inspector and the internet provider have high power and almost no interest in our deadline, which makes them the riskiest. Mitchell et al. (1997) argue that stakeholders draw attention according to their power, legitimacy and urgency. The inspector has all three only at the end, which is exactly when a surprise would hurt most. Olander and Landin (2005) found in construction projects that stakeholders who were analyzed and engaged early caused fewer late disruptions than those discovered during the work, so the architect will hold a pre-application meeting with the city in December. Bourne and Walker (2005) argue that a stakeholder's influence has to be mapped, not assumed, and revisited as the project moves, because those who matter most change over its life. The inspector matters little in January and decisively in May. IT will order the fiber in January, with a weekly check on the install date, and the inspector will walk the site twice before the final inspection.

What this page is doingSorting them.
3

The sponsor gets a one-page status report every Friday. The leadership team hears monthly, and staff get a monthly town hall plus a short email after each milestone. Client service staff, whose phones must keep ringing, help test the cutover. Clients receive a letter in May with our new address and a promise that phone numbers stay the same.

What this page is doingWho hears what.
4

Who outside your organization could stop your project, and when would you first find out?

What this page is doingFor classmates.
5

References

Bourne, L., & Walker, D. H. T. (2005). Visualising and mapping stakeholder influence. Management Decision, 43(5), 649-660. https://doi.org/10.1108/00251740510597680

Mitchell, R. K., Agle, B. R., & Wood, D. J. (1997). Toward a theory of stakeholder identification and salience: Defining the principle of who and what really counts. Academy of Management Review, 22(4), 853-886. https://doi.org/10.5465/amr.1997.9711022105

Olander, S., & Landin, A. (2005). Evaluation of stakeholder influence in the implementation of construction projects. International Journal of Project Management, 23(4), 321-328. https://doi.org/10.1016/j.ijproman.2005.02.002

What the QSO 345 Module 4 instructions ask for

The QSO 345 Module 4 discussion usually turns to stakeholders and communication. Students are asked to identify the people and groups who affect or are affected by a project, analyze their interest and influence, often with a power and interest grid, and explain how the project will engage and communicate with them. Strong posts look beyond the organization to regulators, suppliers, customers and neighbors, explain why particular stakeholders need close management, describe what each needs to know and how often, and connect the analysis to research on stakeholder influence. Replies should ask a classmate about a stakeholder they may have missed or about how a resistant group will be engaged.

How this QSO 345 Module 4 discussion example is built

The post analyzes stakeholders of the Harrow Mutual Insurance Agency move, a fictional relocation of 140 staff in Omaha. A first list held only people inside the agency; a second pass added the City of Omaha's building inspector, the internet provider, the downtown landlord, the agency's insurance carriers and 21,000 clients. Sorting them by power and interest and by the salience test of Mitchell, Agle and Wood, which weighs power, legitimacy and urgency, shows that the inspector and the internet provider could each stop the move. Olander and Landin's study of construction projects supports managing them closely. The post sets out a communication plan by group, from a weekly sponsor report to monthly staff town halls.

Where the QSO 345 Module 4 rubric puts the points

Instructors grading the QSO 345 Module 4 thread look for a complete list of stakeholders inside and outside the organization, a sound analysis of their interest and influence, a clear explanation of which need close management and why, a practical communication or engagement plan, correct use of research and replies that help peers see stakeholders they missed. Posts that score highest explain how a stakeholder's position could change during the project. Points drop when posts list only internal departments, treat all stakeholders the same, describe communication as "keeping everyone informed" without channels or frequency or answer classmates with agreement only. Clear writing and correct citations count too.

QSO 345 Module 4 help: the mistakes that cost points

Start by listing everyone who could affect your project or be affected by it, then push past the organization chart: regulators, inspectors, suppliers, utilities, customers, neighbors and landlords often matter more than internal departments. For each, ask how much power they have over the project and how interested they are, and place them on a grid. Those with high power need close management, even if their interest is low. Then decide what each group needs to hear, from whom, how often and by which channel. A common mistake is listing stakeholders without analyzing them; another is treating a communication plan as a list of meetings. Close by asking classmates which stakeholder could stop their project and how they would find out.

Get QSO 345 Module 4 written to your instructions

Paste the QSO 345 Module 4 prompt and describe your project. A writer identifies its stakeholders inside and outside the organization, sorts them by power and interest or salience, names the ones who could stop the project and plans how each is engaged, with message, channel and frequency, citing stakeholder research. Your first QSO 345 post is free, and a draft reaches you within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 345 papers and related BS Operations Management samples

QSO 345 Module 4 questions, answered

Where can I find a free QSO 345 Module 4 Discussion sample?

This page holds the full QSO 345 Module 4 post: stakeholder analysis and a communication plan for an invented insurance agency's office move.

What is a stakeholder in project management?

Any individual, group or organization that may affect, be affected by or perceive itself to be affected by a project's decisions, activities or outcomes.

What is a power and interest grid?

A tool that places stakeholders by their power over the project and their interest in it, suggesting whether to manage closely, keep satisfied, keep informed or monitor.

What is stakeholder salience?

Mitchell, Agle and Wood's idea that stakeholders get attention according to their power, legitimacy and urgency; those with all three are definitive stakeholders.

What is a communication management plan?

The part of the project plan stating what information each stakeholder needs, who provides it, in what format, how often and through which channel.