| Course | QSO 345 Project Management for CAPM® Certification |
|---|---|
| Module | Module 7 |
| Paper type | undergraduate project reporting project performance with earned value, forecasting cost and finish, processing change requests and planning project closure |
| Length | About 1,160 words, 7 pages |
| Format | APA 7 student paper |
| School | Southern New Hampshire University |
| Program | BS Operations Management |
| Updated | October 2026 |
Free sample paper for QSO 345 Module 7
Behind by a Week and a Quarter: Earned Value, Change Control and Closing Plan for the Harrow Mutual Move
[Student Name]
Southern New Hampshire University
QSO 345: Project Management for CAPM Certification
Project Two: Monitoring, Control and Closing
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Behind by a Week and a Quarter: Earned Value, Change Control and Closing Plan for the Harrow Mutual Move
Introduction
This report covers the relocation of Harrow Mutual Insurance Agency at the end of week 18, Friday, March 5, 2027. Demolition and abatement have finished, and construction, the longest activity on the critical path, is in its fourth week. The project uses earned value management to measure progress against the cost baseline of $2.92 million approved in the plan, with a $180,000 contingency held separately for a total of $3.1 million. The report calculates performance, sets out why the variances arose, projects the final cost and finish date, evaluates two change requests and sets out the closing plan.
Earned Value Status
Earned value at week 18
| Measure | Value |
|---|---|
| Budget at completion (BAC) | $2,920,000 |
| Planned value (PV) | $866,700 |
| Earned value (EV) | $705,000 |
| Actual cost (AC) | $781,000 |
| Schedule variance (EV minus PV) | minus $161,700 |
| Cost variance (EV minus AC) | minus $76,000 |
| Schedule performance index (EV / PV) | 0.81 |
| Cost performance index (EV / AC) | 0.90 |
Planned value comes from the time-phased baseline: $350,000 for design, permits and demolition through week 14, plus four of the 12 weeks of construction budgeted at $1.55 million. Earned value was measured from completed work packages, using the contractor's schedule of values for construction. Actual cost comes from invoices received and accruals for work performed but not yet billed, including a $62,000 draw from contingency for abatement.
Anbari (2003) describes earned value as an integration of scope, schedule and cost, valuable because it shows whether money spent has bought the progress planned. Here it shows that the project has completed about 81 percent of the work planned by week 18 and has spent $1.11 for each dollar of work earned.
Causes of the Variances
Most of the cost variance has one cause. When the abatement contractor lifted the old floor tile in the press hall, the mastic underneath contained asbestos over about 6,000 more square feet than the pre-bid sampling had found, because the sampling had covered the office areas and only two spots in the press hall. Removing it cost $62,000 and nine working days. That accounts for $62,000 of the $76,000 cost variance, and it was a one-time event: the press hall is now clear and no other areas share that floor. The remaining $14,000 comes from framing labor running slightly over in the first weeks of construction.
The schedule variance also comes mostly from abatement. Construction started nine working days late, and the contractor has since recovered about half a week by working Saturdays. SPI is less useful for the schedule than it looks, because it is measured in dollars. Vanhoucke and Vandevoorde (2007), in simulations of project networks, found that the earned schedule method gave more reliable forecasts of project duration than methods based on SPI, especially in the later stages of a project. Earned schedule asks when the work now earned should have been done according to the baseline. The $705,000 earned should have been reached at about week 16.75, so the project is about 1.25 weeks behind. Because the delay is on the critical path and the schedule had about one week of buffer, the move date is at risk unless the time is recovered.
Forecasts
Estimates at completion
| Method | Formula | Estimate |
|---|---|---|
| Variance continues | BAC / CPI | $3,234,800 |
| Variance one-time | AC + (BAC minus EV) | $2,996,000 |
| Abatement one-time, other work at its own CPI | AC + (BAC minus EV) / 0.98 | $3,040,000 |
Lipke et al. (2009) applied statistical methods to the performance indexes, which lets a project manager put a range around a forecast instead of a single figure, and the ranges are widest early, before the indexes have had time to settle. The choice of forecast therefore matters more than its decimals. Assuming the overall CPI of 0.90 continues would forecast $3.23 million, more than the $3.1 million funded, but that would assume more asbestos is coming, which it is not. Treating the whole variance as one-time would ignore the framing overrun. The most realistic forecast treats abatement as one-time and applies the CPI of the other work, $705,000 earned against $719,000 spent, or 0.98, to the remaining work. That gives an estimate at completion of about $3.04 million, within funds, with about $60,000 of contingency left for the remaining risks. The to-complete performance index needed to finish within the $3.1 million is 0.96, which current performance on non-abatement work exceeds.
Change Requests
Change requests at week 18
| Request | Effect | Decision |
|---|---|---|
| CR-07. Second drywall crew for weeks 19 to 24 | Recovers 1.5 weeks on the critical path; costs $18,000 from contingency | Approved by project manager; sponsor informed |
| CR-08. Add a video recording studio for sales | Adds scope; $46,000; three weeks of electrical and acoustic work | Referred to sponsor; deferred to after the move |
CR-07 is a corrective action. A second drywall crew from the general contractor shortens the framing and finishes work by about a week and a half, restoring the buffer before the move. It costs $18,000, within the project manager's authority to release up to $25,000 of contingency per item, so it was approved, logged and reported to the sponsor in the weekly report. After it, about $42,000 of contingency remains against the forecast.
CR-08 came from the sales director, who wants a small studio for recording video quotes. It adds scope outside the charter, costs more than the project manager can approve and would add electrical and acoustic work to the critical path. Under integrated change control it went to the sponsor with this analysis. The sponsor deferred it: the room will be built as a standard office with extra conduit, so a studio can be fitted after the move for about $38,000 from the operating budget.
Closing Plan
The project will close in four steps after the move weekend. First, acceptance: each deliverable will be checked against the acceptance tests the scope statement set, including the certificate of occupancy, workstation test scripts, the 500-record file audit and the landlord's signoff on the old floors, and the sponsor will sign a formal acceptance. Second, contract closure: the contractor's punch list will be finished, retainage released once it is, warranties and as-built drawings collected and each vendor's final invoice reconciled. Third, lessons learned: a session with the team and vendors will record what went well and what did not, beginning with the pre-bid sampling that missed the press hall, and the risk register's closed risks will show which estimates proved right. Fourth, release: team members will return full-time to their departments, the satisfaction survey will run at 60 days and the project files will be archived for the agency.
Conclusion
At week 18 the Harrow Mutual move is 1.25 weeks behind and $76,000 over its earned budget, mostly because of one asbestos discovery. The realistic forecast keeps the project within its $3.1 million, a second drywall crew restores the buffer and the studio waits until after the move. The next report, at week 22, will show whether construction has held the recovered time.
References
Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23. https://doi.org/10.1177/875697280303400403
Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27(4), 400-407. https://doi.org/10.1016/j.ijproman.2008.02.009
Vanhoucke, M., & Vandevoorde, S. (2007). A simulation and evaluation of earned value metrics to forecast the project duration. Journal of the Operational Research Society, 58(10), 1361-1374. https://doi.org/10.1057/palgrave.jors.2602296
What the QSO 345 Module 7 instructions ask for
QSO 345 Project Two usually asks students to monitor and control a project and plan its closure. Expect to report status using earned value management, calculating planned value, earned value, actual cost, schedule and cost variances and the schedule and cost performance indexes; forecast the estimate at completion and, in many versions, the to-complete performance index; explain the causes of variances and recommend corrective action; process one or more change requests through integrated change control; and describe how the project will be closed, including acceptance of deliverables, lessons learned, contract closure and release of resources. Strong projects interpret the numbers rather than only calculating them and choose forecasts that fit the causes.
How this QSO 345 Module 7 project two example is built
The project reports on the Harrow Mutual Insurance Agency move, a fictional relocation in Omaha, at week 18. Planned value is $866,700, earned value $705,000 and actual cost $781,000, giving an SPI of 0.81 and a CPI of 0.90. Most of the cost variance came from $62,000 of extra asbestos abatement, a one-time event; the rest of the work is running near budget, so the estimate at completion is about $3.04 million against $3.1 million in funds. Earned schedule puts the project 1.25 weeks behind, more than its one week of buffer. A second drywall crew is approved, a video studio is deferred and the closing plan is set. Anbari, Lipke and colleagues and Vanhoucke and Vandevoorde support the method.
Where the QSO 345 Module 7 rubric puts the points
Instructors grading QSO 345 Project Two look at correct earned value calculations, accurate interpretation of schedule and cost performance, forecasts chosen to fit the causes of variance, sound corrective actions, change requests evaluated for their effects on scope, schedule, cost and risk and approved at the right level and a complete closing plan. Projects that score highest separate one-time variances from trends, explain what the indexes do and do not show and connect every action to a figure. Credit drops when formulas are misapplied, indexes are reported without meaning, every forecast assumes the same performance, changes bypass change control or closing is a single sentence. Tables, clarity and APA citations count too.
QSO 345 Module 7 help: the mistakes that cost points
Start with three numbers at your status date: planned value from the baseline, earned value from the work actually completed and actual cost from the invoices. Then calculate schedule variance as EV minus PV, cost variance as EV minus AC, SPI as EV divided by PV and CPI as EV divided by AC. Explain what caused each variance and decide whether it is likely to continue, since that decides which estimate at completion to use. Recommend actions tied to the causes. For each change request, state its effect on scope, schedule, cost and risk and who has authority to approve it. Finish with a closing plan. A common mistake is reporting an SPI without saying how many weeks behind it means; another is approving changes informally.
Get QSO 345 Module 7 written to your instructions
Upload the QSO 345 Project Two guidelines and your project data. A writer calculates planned value, earned value, actual cost, variances, SPI, CPI, estimates at completion and the to-complete index, explains the causes, processes change requests through change control and plans closing with acceptance, lessons learned and release of resources. Your first QSO 345 project is free, written and returned in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 345 papers and related BS Operations Management samples
- QSO 345 Module 1 Discussion: Why Moving an Office Is a Project
- QSO 345 Module 2 Project Charter Assignment: Authorizing the Harrow Mutual Move
- QSO 345 Module 3 Project One: Scope, Work Breakdown and Schedule
- QSO 345 Module 4 Discussion: Mapping Who Can Stop the Move
- QSO 345 Module 5 Risk Register Assignment: What Could Keep 140 People From Moving
- QSO 345 Module 6 Discussion: Predictive, Agile or Both for an Office Move?
- QSO 345 Module 8 Discussion: A Furniture Vendor's Hockey Tickets
- QSO 370 Module 8 Discussion: A Credit-Hold Model in January
- FIN 460 Module 3 Milestone One: The Gross Estate and Two Estate Taxes
- PSY 365 Module 4 Project One Leadership and Motivation Analysis: Leadership and motivation analysis of a depot
- FIN 341 Module 2 Milestone One: The TD Bank Incident and Its Compliance Challenges
QSO 345 Module 7 questions, answered
Where can I find a free QSO 345 Module 7 Project Two sample?
This page holds the complete QSO 345 Project Two: earned value at week 18, forecasts, change requests and a closing plan for an invented office move.
What is earned value?
The budgeted value of the work actually completed at a point in time, compared with planned value and actual cost to measure schedule and cost performance.
How are SPI and CPI calculated?
Divide earned value by planned value for the SPI and earned value by actual cost for the CPI; a result below 1.0 means the project is behind schedule or over budget.
What is the estimate at completion?
A forecast of the project's total cost, such as budget at completion divided by CPI when performance will continue, or actual cost plus remaining budget when a variance was one-time.
What is integrated change control?
The process of reviewing, approving or rejecting and managing changes to the project's scope, schedule, cost and plans, with decisions made by those with authority.