What Could Keep 140 People From Moving: Risk Register for the Harrow Mutual Relocation
[Student Name]
Southern New Hampshire University
QSO 345: Project Management for CAPM Certification
Risk Register Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
What Could Keep 140 People From Moving: Risk Register for the Harrow Mutual Relocation
Introduction
The relocation of Harrow Mutual Insurance Agency has a fixed end, the June 30, 2027, lease expiry, a schedule with about one week of buffer and a 1960s building whose condition is only partly known. That combination makes risk management central to the plan rather than a formality. Raz et al. (2002) linked the use of risk management practices to project success, most clearly on projects facing high technological uncertainty, and noted how seldom many of those practices were actually used. This register lists ten threats and two opportunities, rates each, assigns a response, an owner and a trigger and estimates expected monetary value to test the $180,000 contingency in the charter.
Method
The risks came out of a two-hour workshop with the general contractor, the architect, the IT vendor, the human resources lead and the project manager, using the schedule, the budget and the charter's assumptions as prompts. Each assumption was treated as a possible risk: if permits might not come in six weeks, that is a risk. Each risk names what could trigger it, the uncertain event itself and what the event would do to the project. Probability is estimated as a percentage, and impact as the cost of the event if it happens, including the cost of delay, with schedule impact noted separately. The register is ranked by expected monetary value, the probability multiplied by the cost.
Ward and Chapman (2003) argue that project risk management focuses too narrowly on discrete threatening events and should address uncertainty more broadly, including uncertainty in estimates, in the basis of plans and in the parties' objectives. The register therefore includes estimating uncertainty, such as construction bids exceeding the budget, and stakeholder uncertainty, such as staff resistance, alongside physical events.
Threats
Threats in the risk register
| Risk | Probability | Impact | EMV | Response | Owner and trigger |
|---|---|---|---|---|---|
| R1. Old floor tile and mastic contain asbestos beyond the survey, adding abatement work and two weeks | 40% | $90,000 | $36,000 | Mitigate: destructive sampling before bidding | Architect; lab results |
| R2. Construction bids exceed estimate because of material prices | 30% | $120,000 | $36,000 | Transfer: fixed-price contract; value engineering list | Project manager; bid opening |
| R3. Permit review exceeds six weeks, delaying the critical path | 30% | $70,000 | $21,000 | Mitigate: pre-application meeting; expediter | Architect; no comments by week 5 |
| R4. Electrical switchgear lead time exceeds 14 weeks | 35% | $40,000 | $14,000 | Mitigate: contractor orders on award | General contractor; supplier quote |
| R5. Cutover takes longer than four hours | 25% | $20,000 | $5,000 | Mitigate: rehearsal; forward lines to mobiles | Technology vendor; failed rehearsal |
| R6. Staff resist open office, lowering satisfaction | 50% | $10,000 | $5,000 | Mitigate: staff layout groups; quiet rooms | HR lead; town hall feedback |
| R7. Client files lost or misplaced in the move | 10% | $50,000 | $5,000 | Mitigate: scanning; numbered crates; chain of custody | Records clerk; crate count mismatch |
| R8. Fiber install at new address is late | 30% | $15,000 | $4,500 | Mitigate: order in January; backup cable circuit | IT manager; no install date by April 1 |
| R9. A key team member leaves during the project | 15% | $15,000 | $2,250 | Accept: document decisions; name a backup | Project manager; resignation |
| R10. Furniture delivery slips past its float | 20% | $10,000 | $2,000 | Accept: rent temporary desks if needed | Furniture dealer; ship date moves |
| Total | $130,750 |
The two largest expected values, hidden asbestos and high bids, are both linked to the building's age and the construction market, and both are being addressed before the contract is signed. Testing the old floor tile and mastic in December costs about $4,000 and either removes R1 from the register or turns it into a known cost included in the bids. A fixed-price contract transfers much of R2 to the contractor, although the contractor will price that risk into its bid, so the project also keeps a list of $150,000 of design changes, such as fewer glass walls and standard carpet, that can be made if bids come in high.
Opportunities
Opportunities in the risk register
| Opportunity | Probability | Benefit | EMV | Response | Owner |
|---|---|---|---|---|---|
| O1. Utility rebate for efficient lighting and cooling | 60% | $40,000 | $24,000 | Exploit: apply during design | Facilities lead |
| O2. Landlord accepts early return and refunds June rent | 20% | $34,000 | $6,800 | Enhance: offer to restore floors early | Project manager |
The rebate is the more likely opportunity, because the city's utility pays for efficient lighting and heating and cooling equipment if the application is filed before installation. The response is to have the architect specify qualifying equipment and file the application during design. The early return is less likely, but costs little to pursue, since the landlord wants the floors for its conversion. The register counts only O1 against the reserve, because O2 depends on the landlord's schedule rather than ours.
Contingency Reserve
The expected monetary value of the ten threats is $130,750, and of the rebate $24,000, giving a net of about $106,750. The charter's $180,000 contingency therefore covers the expected cost of identified risks with about $73,000 to spare. Expected value is an average, and two of the risks, asbestos and high bids, could both occur, costing $210,000 together, which would exhaust the reserve. That is why both are being reduced before the contract is signed rather than left to the reserve. A separate management reserve for unidentified risks is held by the sponsor rather than the project and is not part of the $3.1 million.
Monitoring the Register
Kutsch and Hall (2005) found that project managers in information technology often avoided or ignored risks that were awkward to raise, such as risks that implied criticism of the client or of their own estimates, so that registers looked complete while the most uncomfortable risks went unmanaged. To guard against that, the register will be reviewed at every weekly site meeting, every owner will report on their triggers and any team member may add a risk without approval. Closed risks will stay on the register with their outcome, so that the project's lessons learned can show which estimates were right. The top five risks will appear on the sponsor's weekly report.
Conclusion
The relocation's biggest risks come from the age of the building and the construction market, and both are being addressed before the contract is signed. The remaining risks have owners, triggers and responses, and the contingency covers their expected cost. The register will be the main agenda item each week until the move.
References
Kutsch, E., & Hall, M. (2005). Intervening conditions on the management of project risk: Dealing with uncertainty in information technology projects. International Journal of Project Management, 23(8), 591-599. https://doi.org/10.1016/j.ijproman.2005.06.009
Raz, T., Shenhar, A. J., & Dvir, D. (2002). Risk management, project success, and technological uncertainty. R&D Management, 32(2), 101-109. https://doi.org/10.1111/1467-9310.00243
Ward, S., & Chapman, C. (2003). Transforming project risk management into project uncertainty management. International Journal of Project Management, 21(2), 97-105. https://doi.org/10.1016/S0263-7863(01)00080-1
What the QSO 345 Module 5 instructions ask for
The QSO 345 Module 5 assignment generally asks students to identify and analyze a project's risks and plan responses. Expect to build a risk register listing each risk's cause and effect, rate probability and impact, often on a scale or as a probability-impact matrix, choose a response strategy for each, assign an owner, and in many versions estimate expected monetary value or a contingency reserve. Strong registers state risks as cause, event and effect, include opportunities as well as threats, use the standard strategies correctly, avoid, transfer, mitigate and accept for threats and exploit, share, enhance and accept for opportunities, and name triggers that tell the owner when to act. The reserve should be tied to the analysis.
How this QSO 345 Module 5 risk register assignment example is built
The assignment builds the risk register for the Harrow Mutual Insurance Agency move, a fictional relocation in Omaha. Ten threats include asbestos found beyond the survey, a permit delay, a long lead time for electrical switchgear, a late fiber install, a cutover that runs longer than four hours and staff resistance to an open office. Two opportunities are a utility rebate for efficient lighting and cooling and an early return of the leased floors. Each risk has a probability, cost impact, response, owner and trigger. Expected monetary value totals about $131,000 for threats and $24,000 for opportunities, which the $180,000 contingency covers. Raz, Shenhar and Dvir, Ward and Chapman and Kutsch and Hall inform the method.
Where the QSO 345 Module 5 rubric puts the points
The QSO 345 risk register assignment is generally graded on identifying risks specific to the project, describing each as cause, event and effect, rating probability and impact consistently, choosing appropriate response strategies, assigning owners and triggers, including opportunities and connecting the analysis to a contingency reserve. The strongest registers show that the highest-rated risks receive the most effort and explain how the register will be reviewed. Credit drops when risks are generic, such as "bad weather," ratings are inconsistent, every response is "monitor," owners are departments rather than people or roles or the reserve is a guess. Tables, clear writing and APA citations complete the grade.
QSO 345 Module 5 help: the mistakes that cost points
Start by listing what could go wrong or better than planned, using your schedule, budget and assumptions as prompts: each assumption is a possible risk. Write each risk in three parts: what could set it off, the uncertain event and what it would do to scope, time or cost. Rate probability and impact on a consistent scale or in dollars and weeks. Choose a response: avoid by changing the plan, transfer by contract or insurance, mitigate by reducing likelihood or impact or accept with a reserve. Give each an owner and a trigger, the early warning that tells the owner to act. Multiply probability by cost to estimate expected monetary value and compare the total with your reserve. A common mistake is listing risks without responses; another is forgetting opportunities.
Get QSO 345 Module 5 written to your instructions
Share the QSO 345 Module 5 instructions and describe your project. A writer identifies threats and opportunities, rates probability and impact, chooses avoid, transfer, mitigate, accept, exploit or enhance responses, names owners and triggers, estimates expected monetary value and tests the contingency reserve, citing risk research. Your first QSO 345 risk register costs nothing and is returned within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 345 papers and related BS Operations Management samples
- QSO 345 Module 1 Discussion: Why Moving an Office Is a Project
- QSO 345 Module 2 Project Charter Assignment: Authorizing the Harrow Mutual Move
- QSO 345 Module 3 Project One: Scope, Work Breakdown and Schedule
- QSO 345 Module 4 Discussion: Mapping Who Can Stop the Move
- QSO 345 Module 6 Discussion: Predictive, Agile or Both for an Office Move?
- QSO 345 Module 7 Project Two: Earned Value at Week 18
- QSO 345 Module 8 Discussion: A Furniture Vendor's Hockey Tickets
- MKT 410 Module 8 Discussion: Privacy and the Limits of Tracking
- OL 326 Module 1 Discussion: Business and Society
- FIN 335 Module 4 Project One: A Memo on the Underwater Bond Portfolio
- QSO 260 Module 8 Discussion: A Dashboard the Owner Will Open
QSO 345 Module 5 questions, answered
Where can I find a free QSO 345 Module 5 Risk Register Assignment sample?
The complete QSO 345 Module 5 assignment is on this page: a risk register with responses, owners and expected monetary value for an invented office move.
What is a risk register?
A document listing a project's identified risks with their causes, probability, impact, response strategies, owners, triggers and status, updated throughout the project.
What are the risk response strategies?
For threats, avoid, transfer, mitigate and accept, and escalate when outside the project's authority; for opportunities, exploit, share, enhance and accept.
What is expected monetary value?
The probability of a risk multiplied by its cost or benefit, summed across risks to estimate the reserve needed for uncertain events.
What is a risk trigger?
An early warning sign that a risk is about to occur or has occurred, telling the risk owner it is time to carry out the planned response.