QSO 345 Module 5 Risk Register Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 345 Module 5 Risk Register Assignment sample builds a project risk register with probability and impact ratings, response strategies, owners, triggers and a contingency reserve. SNHU QSO 345 (QSO-345) assigns risk management in Module 5 of its BS Operations Management course on project management for the CAPM exam. The project is the relocation of Harrow Mutual Insurance Agency, an invented Omaha agency, to a renovated building by June 30, 2027. The register for the move lists ten specific threats and two opportunities, rates each, assigns responses and owners, estimates expected monetary value and tests whether the $180,000 contingency is enough.

CourseQSO 345 Project Management for CAPM® Certification
ModuleModule 5
Paper typeundergraduate assignment building a project risk register with probability and impact ratings, response strategies, owners, triggers and a contingency reserve
LengthAbout 1,050 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 345 Module 5

1

What Could Keep 140 People From Moving: Risk Register for the Harrow Mutual Relocation

[Student Name]

Southern New Hampshire University

QSO 345: Project Management for CAPM Certification

Risk Register Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe risks, ratings and costs for Harrow Mutual in this QSO 345 assignment are made up.
2

What Could Keep 140 People From Moving: Risk Register for the Harrow Mutual Relocation

Introduction

The relocation of Harrow Mutual Insurance Agency has a fixed end, the June 30, 2027, lease expiry, a schedule with about one week of buffer and a 1960s building whose condition is only partly known. That combination makes risk management central to the plan rather than a formality. Raz et al. (2002) linked the use of risk management practices to project success, most clearly on projects facing high technological uncertainty, and noted how seldom many of those practices were actually used. This register lists ten threats and two opportunities, rates each, assigns a response, an owner and a trigger and estimates expected monetary value to test the $180,000 contingency in the charter.

What this page is doingPlaces risk planning in the project.
3

Method

The risks came out of a two-hour workshop with the general contractor, the architect, the IT vendor, the human resources lead and the project manager, using the schedule, the budget and the charter's assumptions as prompts. Each assumption was treated as a possible risk: if permits might not come in six weeks, that is a risk. Each risk names what could trigger it, the uncertain event itself and what the event would do to the project. Probability is estimated as a percentage, and impact as the cost of the event if it happens, including the cost of delay, with schedule impact noted separately. The register is ranked by expected monetary value, the probability multiplied by the cost.

Ward and Chapman (2003) argue that project risk management focuses too narrowly on discrete threatening events and should address uncertainty more broadly, including uncertainty in estimates, in the basis of plans and in the parties' objectives. The register therefore includes estimating uncertainty, such as construction bids exceeding the budget, and stakeholder uncertainty, such as staff resistance, alongside physical events.

What this page is doingExplains how risks were identified and rated.
4

Threats

Threats in the risk register

RiskProbabilityImpactEMVResponseOwner and trigger
R1. Old floor tile and mastic contain asbestos beyond the survey, adding abatement work and two weeks40%$90,000$36,000Mitigate: destructive sampling before biddingArchitect; lab results
R2. Construction bids exceed estimate because of material prices30%$120,000$36,000Transfer: fixed-price contract; value engineering listProject manager; bid opening
R3. Permit review exceeds six weeks, delaying the critical path30%$70,000$21,000Mitigate: pre-application meeting; expediterArchitect; no comments by week 5
R4. Electrical switchgear lead time exceeds 14 weeks35%$40,000$14,000Mitigate: contractor orders on awardGeneral contractor; supplier quote
R5. Cutover takes longer than four hours25%$20,000$5,000Mitigate: rehearsal; forward lines to mobilesTechnology vendor; failed rehearsal
R6. Staff resist open office, lowering satisfaction50%$10,000$5,000Mitigate: staff layout groups; quiet roomsHR lead; town hall feedback
R7. Client files lost or misplaced in the move10%$50,000$5,000Mitigate: scanning; numbered crates; chain of custodyRecords clerk; crate count mismatch
R8. Fiber install at new address is late30%$15,000$4,500Mitigate: order in January; backup cable circuitIT manager; no install date by April 1
R9. A key team member leaves during the project15%$15,000$2,250Accept: document decisions; name a backupProject manager; resignation
R10. Furniture delivery slips past its float20%$10,000$2,000Accept: rent temporary desks if neededFurniture dealer; ship date moves
Total$130,750

The two largest expected values, hidden asbestos and high bids, are both linked to the building's age and the construction market, and both are being addressed before the contract is signed. Testing the old floor tile and mastic in December costs about $4,000 and either removes R1 from the register or turns it into a known cost included in the bids. A fixed-price contract transfers much of R2 to the contractor, although the contractor will price that risk into its bid, so the project also keeps a list of $150,000 of design changes, such as fewer glass walls and standard carpet, that can be made if bids come in high.

What this page is doingLists the main risks and responses.
5

Opportunities

Opportunities in the risk register

OpportunityProbabilityBenefitEMVResponseOwner
O1. Utility rebate for efficient lighting and cooling60%$40,000$24,000Exploit: apply during designFacilities lead
O2. Landlord accepts early return and refunds June rent20%$34,000$6,800Enhance: offer to restore floors earlyProject manager

The rebate is the more likely opportunity, because the city's utility pays for efficient lighting and heating and cooling equipment if the application is filed before installation. The response is to have the architect specify qualifying equipment and file the application during design. The early return is less likely, but costs little to pursue, since the landlord wants the floors for its conversion. The register counts only O1 against the reserve, because O2 depends on the landlord's schedule rather than ours.

What this page is doingLists risks with positive effects.
6

Contingency Reserve

The expected monetary value of the ten threats is $130,750, and of the rebate $24,000, giving a net of about $106,750. The charter's $180,000 contingency therefore covers the expected cost of identified risks with about $73,000 to spare. Expected value is an average, and two of the risks, asbestos and high bids, could both occur, costing $210,000 together, which would exhaust the reserve. That is why both are being reduced before the contract is signed rather than left to the reserve. A separate management reserve for unidentified risks is held by the sponsor rather than the project and is not part of the $3.1 million.

What this page is doingTests whether the reserve is enough.
7

Monitoring the Register

Kutsch and Hall (2005) found that project managers in information technology often avoided or ignored risks that were awkward to raise, such as risks that implied criticism of the client or of their own estimates, so that registers looked complete while the most uncomfortable risks went unmanaged. To guard against that, the register will be reviewed at every weekly site meeting, every owner will report on their triggers and any team member may add a risk without approval. Closed risks will stay on the register with their outcome, so that the project's lessons learned can show which estimates were right. The top five risks will appear on the sponsor's weekly report.

What this page is doingExplains how risks will be kept current.
8

Conclusion

The relocation's biggest risks come from the age of the building and the construction market, and both are being addressed before the contract is signed. The remaining risks have owners, triggers and responses, and the contingency covers their expected cost. The register will be the main agenda item each week until the move.

What this page is doingSummarizes the risk picture.
9

References

Kutsch, E., & Hall, M. (2005). Intervening conditions on the management of project risk: Dealing with uncertainty in information technology projects. International Journal of Project Management, 23(8), 591-599. https://doi.org/10.1016/j.ijproman.2005.06.009

Raz, T., Shenhar, A. J., & Dvir, D. (2002). Risk management, project success, and technological uncertainty. R&D Management, 32(2), 101-109. https://doi.org/10.1111/1467-9310.00243

Ward, S., & Chapman, C. (2003). Transforming project risk management into project uncertainty management. International Journal of Project Management, 21(2), 97-105. https://doi.org/10.1016/S0263-7863(01)00080-1

What the QSO 345 Module 5 instructions ask for

The QSO 345 Module 5 assignment generally asks students to identify and analyze a project's risks and plan responses. Expect to build a risk register listing each risk's cause and effect, rate probability and impact, often on a scale or as a probability-impact matrix, choose a response strategy for each, assign an owner, and in many versions estimate expected monetary value or a contingency reserve. Strong registers state risks as cause, event and effect, include opportunities as well as threats, use the standard strategies correctly, avoid, transfer, mitigate and accept for threats and exploit, share, enhance and accept for opportunities, and name triggers that tell the owner when to act. The reserve should be tied to the analysis.

How this QSO 345 Module 5 risk register assignment example is built

The assignment builds the risk register for the Harrow Mutual Insurance Agency move, a fictional relocation in Omaha. Ten threats include asbestos found beyond the survey, a permit delay, a long lead time for electrical switchgear, a late fiber install, a cutover that runs longer than four hours and staff resistance to an open office. Two opportunities are a utility rebate for efficient lighting and cooling and an early return of the leased floors. Each risk has a probability, cost impact, response, owner and trigger. Expected monetary value totals about $131,000 for threats and $24,000 for opportunities, which the $180,000 contingency covers. Raz, Shenhar and Dvir, Ward and Chapman and Kutsch and Hall inform the method.

Where the QSO 345 Module 5 rubric puts the points

The QSO 345 risk register assignment is generally graded on identifying risks specific to the project, describing each as cause, event and effect, rating probability and impact consistently, choosing appropriate response strategies, assigning owners and triggers, including opportunities and connecting the analysis to a contingency reserve. The strongest registers show that the highest-rated risks receive the most effort and explain how the register will be reviewed. Credit drops when risks are generic, such as "bad weather," ratings are inconsistent, every response is "monitor," owners are departments rather than people or roles or the reserve is a guess. Tables, clear writing and APA citations complete the grade.

QSO 345 Module 5 help: the mistakes that cost points

Start by listing what could go wrong or better than planned, using your schedule, budget and assumptions as prompts: each assumption is a possible risk. Write each risk in three parts: what could set it off, the uncertain event and what it would do to scope, time or cost. Rate probability and impact on a consistent scale or in dollars and weeks. Choose a response: avoid by changing the plan, transfer by contract or insurance, mitigate by reducing likelihood or impact or accept with a reserve. Give each an owner and a trigger, the early warning that tells the owner to act. Multiply probability by cost to estimate expected monetary value and compare the total with your reserve. A common mistake is listing risks without responses; another is forgetting opportunities.

Get QSO 345 Module 5 written to your instructions

Share the QSO 345 Module 5 instructions and describe your project. A writer identifies threats and opportunities, rates probability and impact, chooses avoid, transfer, mitigate, accept, exploit or enhance responses, names owners and triggers, estimates expected monetary value and tests the contingency reserve, citing risk research. Your first QSO 345 risk register costs nothing and is returned within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 345 papers and related BS Operations Management samples

QSO 345 Module 5 questions, answered

Where can I find a free QSO 345 Module 5 Risk Register Assignment sample?

The complete QSO 345 Module 5 assignment is on this page: a risk register with responses, owners and expected monetary value for an invented office move.

What is a risk register?

A document listing a project's identified risks with their causes, probability, impact, response strategies, owners, triggers and status, updated throughout the project.

What are the risk response strategies?

For threats, avoid, transfer, mitigate and accept, and escalate when outside the project's authority; for opportunities, exploit, share, enhance and accept.

What is expected monetary value?

The probability of a risk multiplied by its cost or benefit, summed across risks to estimate the reserve needed for uncertain events.

What is a risk trigger?

An early warning sign that a risk is about to occur or has occurred, telling the risk owner it is time to carry out the planned response.