QSO 345 Module 3 Project One Example

Reviewed by Portia Lambrick, MBA

This QSO 345 Module 3 Project One sample develops a scope statement, a work breakdown structure, an activity network with its critical path and a cost baseline for one project. SNHU QSO 345 (QSO-345) asks for this planning work in Module 3 of its BS Operations Management course on project management for the CAPM exam. The project is the relocation of Harrow Mutual Insurance Agency, an invented Omaha agency, to a renovated building by June 30, 2027. The plan breaks the work into 31 work packages, sequences the activities, finds a 33-week critical path through design, construction, technology, inspection and the move and lays out a time-phased cost baseline.

CourseQSO 345 Project Management for CAPM® Certification
ModuleModule 3
Paper typeundergraduate project developing a scope statement, work breakdown structure, activity network with critical path and cost baseline for one project
LengthAbout 1,080 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 345 Module 3

1

Thirty-Three Weeks to Midtown: Scope, Work Breakdown Structure and Schedule for the Harrow Mutual Move

[Student Name]

Southern New Hampshire University

QSO 345: Project Management for CAPM Certification

Project One: Scope, WBS and Schedule

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe scope, work packages, durations and costs for Harrow Mutual in this QSO 345 project are fictional.
2

Thirty-Three Weeks to Midtown: Scope, Work Breakdown Structure and Schedule for the Harrow Mutual Move

Introduction

The charter authorized Harrow Mutual Insurance Agency's move from leased downtown floors to a renovated building in midtown, with all staff working there by June 25, 2027, and a budget of $3.1 million. This project turns the charter into a plan: a scope statement, a work breakdown structure, an activity list and network with its critical path and a time-phased cost baseline. Dvir et al. (2003) found that planning activities, especially defining requirements and specifications, were associated with project success, so this plan was built after four weeks of gathering requirements from every team.

What this page is doingLinks the plan to the charter.
3

Scope Statement

The project will produce six deliverables. A renovated building, accepted when the city issues a certificate of occupancy and a walk-through finds no open punch-list items affecting use. Installed technology, accepted when every workstation, phone and meeting room passes a test script. Installed furniture, accepted when every workstation and room matches the approved layout. Prepared staff, accepted when every employee has toured the building and received a seat assignment and move kit. A completed move, accepted when every employee can work at a tested workstation and the file audit finds no missing records. Returned leased floors, accepted when the landlord signs off on their condition. Exclusions are as stated in the charter, including insurance software and team restructuring. Constraints are the June 30 lease end, the $3.1 million budget and the requirement that client service continue throughout. Assumptions include permit approval within six weeks of submission and contractor availability in January.

What this page is doingDefines deliverables, acceptance, exclusions and constraints.
4

Work Breakdown Structure

The work breakdown structure has the project at level one, six deliverables at level two and 31 work packages at level three. The renovated building includes design and engineering, permits, contractor procurement, demolition and abatement, framing and finishes, electrical, heating and cooling, plumbing, fire protection and inspections. Installed technology includes network design, cabling, wireless, telephones, meeting room audio and video, internet service and testing. Installed furniture includes layout, selection, ordering, delivery and installation. Prepared staff includes the communication plan, building tours, seat assignments, move kits and records purge. The completed move includes mover procurement, the move weekend, systems cutover and day-one support. Returned leased floors include restoration and landlord inspection. Project management, with planning, reporting and closing, sits alongside as its own branch. Each work package has one owner: the architect, the general contractor, the technology vendor, the furniture dealer, human resources, the operations team or the project manager.

What this page is doingDecomposes the work into deliverables and packages.
5

Activities, Durations and Dependencies

Key activities, durations and predecessors

ActivityDurationPredecessor
A. Design and permits8 weeksStart
B. Contractor bidding and award3 weeksA
C. Demolition and abatement3 weeksB
D. Construction12 weeksC
E. Furniture selection and order2 weeksA
F. Furniture manufacture and delivery12 weeksE
G. Technology installation3 weeksD
H. Furniture installation2 weeksD, F
I. Final inspection and certificate of occupancy1 weekG, H
J. Move weekend and systems cutover1 weekI
K. Restore and return leased floors2 weeksJ
L. Staff preparation16 weeksB

Durations were estimated from the architect's and contractor's experience with similar buildings, vendor quotes and, for staff preparation, from human resources' plan. Buehler et al. (1994) showed that people expect to finish their own tasks sooner than they do, because their attention stays on how the work should go and drifts away from how similar work went before. To counter that, durations for design, permits and construction were taken from the contractor's records of past jobs rather than from optimistic plans, and construction includes one week for weather and inspections.

What this page is doingSequences the work.
6

Network and Critical Path

Working forward from the start on November 2, 2026, the path A, B, C, D, G, I, J, K takes 8 + 3 + 3 + 12 + 3 + 1 + 1 + 2 = 33 weeks, ending on June 18, 2027, a week ahead of the charter's June 25 target. The furniture path, A, E, F, H, takes 8 + 2 + 12 + 2 = 24 weeks to reach the end of furniture installation, but furniture installation cannot start until construction ends in week 26, so furniture delivery has about five weeks of float: it is planned for week 22, and installation, which takes two weeks, need not start until week 27 for inspection to begin on time. Staff preparation, which runs from the end of week 11 for 16 weeks, ends in week 27 and has about three weeks of float before the move. The critical path is therefore the renovation chain followed by technology, inspection, the move and decommissioning. With the lease ending on June 30, the project has about one week of buffer beyond the critical path, which the project manager will protect.

Flyvbjerg (2014) found that large projects tend to overrun because of optimism and, in some cases, strategic misrepresentation, and that the risk compounds when schedules have little slack. A one-week buffer is thin, which is why construction, the longest critical activity, will be tracked weekly.

What this page is doingIdentifies what determines the finish date.
7

Cost Baseline

Costs were estimated for each work package, using vendor quotes for construction, technology, furniture and movers and the architect's fee proposal. The cost baseline, excluding the $180,000 contingency, is $2.92 million. Spread by schedule, about $350,000 is spent in the first 14 weeks on design, permits and demolition; about $1.55 million in weeks 15 to 26 for construction, along with a furniture deposit; about $0.84 million in weeks 27 to 31 for technology, furniture balance and the move; and about $0.18 million in weeks 32 and 33 for restoration and closing. This time-phased baseline will be used for earned value reporting.

What this page is doingTies costs to the work and spreads them over time.
8

Management Implications

Because the critical path runs through construction, any construction delay delays the move unless recovered. The project manager will hold a weekly site meeting with the contractor, track construction progress against the schedule and decide early whether to add crews. Furniture and staff preparation have float and can be managed monthly.

The plan also sets two thresholds for action. If construction falls more than three working days behind its weekly targets, the project manager and the contractor will agree on a recovery plan within a week, using extra crews or Saturday work. If any work package's cost runs more than 5 percent above its estimate, its owner will explain why at the next site meeting and the forecast will be updated. Once approved, the scope, schedule and cost baselines in this plan can be changed only through change control.

What this page is doingExplains how the plan will be used.
9

References

Buehler, R., Griffin, D., & Ross, M. (1994). Exploring the "planning fallacy": Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366-381. https://doi.org/10.1037/0022-3514.67.3.366

Dvir, D., Raz, T., & Shenhar, A. J. (2003). An empirical analysis of the relationship between project planning and project success. International Journal of Project Management, 21(2), 89-95. https://doi.org/10.1016/S0263-7863(02)00012-1

Flyvbjerg, B. (2014). What you should know about megaprojects and why: An overview. Project Management Journal, 45(2), 6-19. https://doi.org/10.1002/pmj.21409

What the QSO 345 Module 3 instructions ask for

QSO 345 Project One typically asks students to plan a project's scope and schedule. Expect to write a scope statement that describes deliverables, acceptance criteria, exclusions, constraints and assumptions; build a work breakdown structure that decomposes the project into deliverables and work packages; define activities with durations and dependencies; draw a network diagram; identify the critical path and float; and, in many versions, estimate costs to create a budget baseline. Strong projects organize the work breakdown structure around deliverables rather than departments, show logical dependencies, calculate the critical path correctly and explain which activities have float and what that means for management. Estimates should state their basis.

How this QSO 345 Module 3 project one example is built

The project plans the relocation of Harrow Mutual Insurance Agency, a made-up Omaha agency. The scope statement lists six deliverables with acceptance criteria, from an occupancy-ready building to returned leased floors, and names exclusions such as insurance software. The work breakdown structure decomposes the move into six level-two deliverables and 31 work packages. Activities with durations and finish-to-start dependencies produce a 33-week critical path, design and permits, contractor award, demolition, construction, technology installation, inspection, the move and decommissioning, inside a 34-week window. Furniture, with a 12-week lead time, has five weeks of float. Dvir, Raz and Shenhar on planning, Buehler, Griffin and Ross on the planning fallacy and Flyvbjerg on overruns explain why estimates were padded where uncertainty is highest.

Where the QSO 345 Module 3 rubric puts the points

Instructors grading QSO 345 Project One look at a complete scope statement with acceptance criteria and exclusions, a work breakdown structure that decomposes deliverables to work packages without gaps or overlaps, activities with realistic durations and logical dependencies, a correctly calculated critical path and float, a cost baseline tied to the work packages and explanation of estimating assumptions. Projects that score highest show the network clearly, explain why the critical path matters for management and identify where estimates are most uncertain. Credit drops when the work breakdown structure follows the organization chart, dependencies are missing, the critical path is wrong or costs are not linked to work. Tables, diagrams described clearly and APA citations count too.

QSO 345 Module 3 help: the mistakes that cost points

Begin with the scope statement: list each deliverable and how it will be accepted, then what is excluded and what constraints apply. Build the work breakdown structure from the top down, breaking each deliverable into smaller deliverables until each work package can be estimated and assigned to one owner, and check that every piece of work appears once. Turn work packages into activities, estimate each duration and decide what must finish before each can start. Draw the network and calculate the earliest and latest start and finish for each activity; the path with no float is the critical path. Add costs to work packages and spread them over time. A common mistake is a work breakdown structure organized by department; another is a schedule with no dependencies, which cannot show a critical path.

Get QSO 345 Module 3 written to your instructions

Upload the QSO 345 Project One guidelines and your charter. A writer turns it into a scope statement with acceptance criteria and exclusions, a work breakdown structure that reaches the work package level, an activity list with durations and dependencies, a network diagram with the critical path and float and a time-phased cost baseline. Your first QSO 345 project is free and lands in your inbox in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 345 papers and related BS Operations Management samples

QSO 345 Module 3 questions, answered

Where can I find a free QSO 345 Module 3 Project One sample?

This page holds the complete QSO 345 Project One: scope statement, work breakdown structure, critical path schedule and cost baseline for an invented office move.

What is a work breakdown structure?

A hierarchical decomposition of the project's total scope into deliverables and smaller components until it reaches work packages, each of which can be estimated, scheduled and assigned.

What is the critical path?

The chain of linked activities with the greatest total duration, which sets the shortest time in which the project can finish; its activities have zero float.

What is float in a schedule?

The amount of time an activity can be delayed without delaying the project's finish date, also called total float or slack.

What is a scope statement?

A document describing the project's deliverables, acceptance criteria, exclusions, constraints and assumptions, which defines what the project will and will not produce.