Module One Discussion
A Lease That Ends on June 30
I am the operations manager at Harrow Mutual Insurance Agency, an independent agency in Omaha with 140 employees who sell and service home, auto and business insurance. Our lease on three floors of a downtown office tower ends on June 30, 2027, and the landlord will not extend it. Last month the agency bought a vacant printing plant in midtown, one floor of about 42,000 square feet, and the chief executive asked me to lead the move. We have a budget of $3.1 million for renovation, technology, furniture and moving.
The move fits the standard definition of a project, a temporary endeavor to create a unique result. It is temporary: it starts this November and ends when the last employee is working in the new building and the old floors are returned. It is unique: we have never moved, and the result, a renovated building fitted to our teams, has never existed before. What we are forming is a temporary organization in the sense project researchers use (Turner & Müller, 2003), a group set up to deliver one change and staffed with people on loan: a team borrowed from IT, facilities, finance, human resources and every sales and service department, which will disband once the move is complete. Our ongoing work, issuing policies and handling claims, is operations, and it must continue every day while the move happens.
None of the team reports to me. My job is to plan the work, coordinate the architect, the contractor and the vendors, track the schedule and budget, manage risks and keep the chief executive and staff informed. Pinto and Slevin (1987) identified ten factors that experienced managers saw as critical to project success, beginning with a clear mission and top management support and including schedules, client consultation, personnel, technical tasks, client acceptance, monitoring, communication and troubleshooting. We have the first two. Dvir et al. (2003) linked success to how much work went into setting requirements and technical specifications at the start, which tells me to spend the first weeks pinning down what each team needs in the new building before the architect finishes drawings.
Which part of your own work is really a project, and what would mark the moment it is finished?
References
Dvir, D., Raz, T., & Shenhar, A. J. (2003). An empirical analysis of the relationship between project planning and project success. International Journal of Project Management, 21(2), 89-95. https://doi.org/10.1016/S0263-7863(02)00012-1
Pinto, J. K., & Slevin, D. P. (1987). Critical factors in successful project implementation. IEEE Transactions on Engineering Management, EM-34(1), 22-27. https://doi.org/10.1109/TEM.1987.6498856
Turner, J. R., & Müller, R. (2003). On the nature of the project as a temporary organization. International Journal of Project Management, 21(1), 1-8. https://doi.org/10.1016/S0263-7863(02)00020-0
What the QSO 345 Module 1 instructions ask for
QSO 345 begins with introductions and the basic ideas of project management: what a project is, how it differs from ongoing operations, what a project manager does and why organizations pursue certification such as the CAPM. Students usually describe a project they know or have worked on. Strong posts use the standard definition, a temporary endeavor undertaken to create a unique product, service or result, and show each part of it in the example, describe the project's constraints of scope, schedule, cost and quality, and explain the project manager's role in coordinating people who do not report to them. Replies should ask a classmate what would mark the end of their project or who its sponsor is.
How this QSO 345 Module 1 discussion example is built
The post introduces the course's project at Harrow Mutual Insurance Agency, a fictional independent agency with 140 employees in Omaha. Its downtown lease ends June 30, 2027, and it has bought a 42,000-square-foot former printing plant to renovate. The move is a project because it is temporary, with a hard end date, and unique, since the agency has never moved; it has a $3.1 million budget and a team drawn from IT, facilities, finance and every department. The post describes the operations manager's new role as project manager and draws on Turner and Müller's view of the project as a temporary organization, Pinto and Slevin's ten critical success factors and the Dvir, Raz and Shenhar finding that planning effort is linked to success.
Where the QSO 345 Module 1 rubric puts the points
Instructors grading the first QSO 345 thread look for an accurate definition of a project, a clear contrast with operations, a specific example showing what makes it temporary and unique, attention to the constraints of scope, time, cost and quality, a realistic account of the project manager's role, correct use of research and replies that help peers sharpen their examples. Posts that score highest name the sponsor, the deliverables and the end point. Points drop when posts call any task a project, skip the constraints, describe the manager as a boss with direct authority or answer classmates with greetings alone. Clear writing and correct citations count too.
QSO 345 Module 1 help: the mistakes that cost points
Choose something you have worked on and test it against the definition: does it have a clear start and end, and does it produce something that has not been produced in exactly that way before? If it repeats every week, it is operations, even if it is complicated. Then name its scope, deadline, budget and quality standards, the sponsor who authorized it and the people from different departments it needs. A common mistake is choosing ongoing work, such as monthly reporting; another is describing the project manager as if everyone reported to them, when most project managers lead through influence. Mention one thing that would have to be planned early. Close by asking classmates what marks the end of their projects.
Get QSO 345 Module 1 written to your instructions
Paste the QSO 345 Module 1 prompt and describe some work you are involved in. A writer explains whether it is a project or operations, what makes it temporary and unique, what a project manager would coordinate and why early planning matters, using project management research, and asks QSO 345 classmates a question about their own projects. Your first QSO 345 post is free, back in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 345 papers and related BS Operations Management samples
- QSO 345 Module 2 Project Charter Assignment: Authorizing the Harrow Mutual Move
- QSO 345 Module 3 Project One: Scope, Work Breakdown and Schedule
- QSO 345 Module 4 Discussion: Mapping Who Can Stop the Move
- QSO 345 Module 5 Risk Register Assignment: What Could Keep 140 People From Moving
- QSO 345 Module 6 Discussion: Predictive, Agile or Both for an Office Move?
- QSO 345 Module 7 Project Two: Earned Value at Week 18
- QSO 345 Module 8 Discussion: A Furniture Vendor's Hockey Tickets
- INT 221 Module 1 Discussion: Why Almost Every Invoice Says Dollars
- MKT 225 Module 6 Email Campaign Assignment: A Weekday Email and Retargeting Campaign
- FIN 460 Module 3 Milestone One: The Gross Estate and Two Estate Taxes
- QSO 260 Module 6 Discussion: The Driver Who Looked Worst and Was Best
QSO 345 Module 1 questions, answered
Where can I find a free QSO 345 Module 1 Discussion sample?
This page holds the full QSO 345 Module 1 post: an invented insurance agency's office relocation described as a project, with the project manager's role.
What is a project?
A temporary endeavor undertaken to create a unique product, service or result, with a defined beginning and end, as distinct from ongoing, repetitive operations.
What does a project manager do?
Leads the team assigned to achieve the project's objectives, planning the work, coordinating people across departments, managing scope, schedule, cost, quality and risk and communicating with stakeholders.
What is the CAPM certification?
The Certified Associate in Project Management, an entry-level credential from the Project Management Institute that tests knowledge of project management terms and processes.
What are the constraints of a project?
Commonly scope, schedule, cost and quality, along with resources and risk; changing one, such as adding scope, usually affects the others.