Free sample paper for QSO 349 Module 1
Module One Discussion
Four Contracts and Three Engineers
I work in the engineering office of the Casco Narrows Ferry District, a public operator that carries about 410,000 passengers a year between the mainland terminal and two islands. Our oldest boat was built in 1979, burns about 61,000 gallons of diesel a year and needs a new engine it is not worth giving. The district's board has approved $14.8 million to replace it with a 149-passenger hybrid-electric ferry that charges for about twelve minutes at the mainland dock, along with the charger and the electrical work at the terminal.
We will not design or build anything ourselves. About $13.9 million, roughly 94 percent of the budget, will flow through four contracts: a naval architect for the design, a shipyard for the vessel, an electrical contractor for the charger and an owner's representative to watch the shipyard for us. Our office has three engineers, none of whom has bought a boat. If those contracts are written badly, no amount of good project management afterward will rescue the schedule or the price.
Turner and Simister (2001) argue that a contract is the means by which the buyer motivates the seller to pursue the buyer's objectives, and that the right form depends on how uncertain the product and the process are. A hybrid ferry is uncertain in both: the battery system is new to the district, and the yard will be building a design it has not built before. Thai (2001) points out that public buyers must balance goals that pull against each other, such as low price, quality, open competition, speed and accountability for grant money. For us that means choosing contract types and selection methods we can defend to the board and to auditors, not only ones that work. Bajari and Tadelis (2001) add a warning that applies to all four contracts: whatever the documents leave out will be settled later through change orders, after the competition that kept prices honest is over.
Before any seller sees a document, we must decide what to design ourselves and what to buy, how to split the purchase into contracts and which contract type fits each piece.
How much of your project's budget goes to outside sellers, and which one could sink the schedule?
References
Bajari, P., & Tadelis, S. (2001). Incentives versus transaction costs: A theory of procurement contracts. RAND Journal of Economics, 32(3), 387-407. https://doi.org/10.2307/2696361
Thai, K. V. (2001). Public procurement re-examined. Journal of Public Procurement, 1(1), 9-50. https://doi.org/10.1108/JOPP-01-01-2001-B001
Turner, J. R., & Simister, S. J. (2001). Project contract management and a theory of organization. International Journal of Project Management, 19(8), 457-464. https://doi.org/10.1016/S0263-7863(01)00051-5
What the QSO 349 Module 1 instructions ask for
QSO 349 opens with introductions and the place of procurement in project management. Students usually describe a project and explain how buying goods and services from outside sellers shapes it: how much of the scope is delivered under contract, which procurement processes are involved, from planning purchases to closing contracts, and how the choice of contract shares risk between buyer and seller. Strong posts give figures for how much of the project is procured, explain why the buying organization cannot or should not do the work itself, connect contract choices to risk and cite procurement research. Replies should ask a classmate which purchase in their project carries the most risk or who in their organization administers contracts.
How this QSO 349 Module 1 discussion example is built
The post introduces the purchase used throughout the course: the Casco Narrows Ferry District, a fictional public operator carrying 410,000 passengers a year to two Maine islands, is replacing its 1979 diesel ferry with a 149-passenger hybrid-electric boat and a charger at the mainland terminal on a $14.8 million budget. About $13.9 million, roughly 94 percent, will be spent through four contracts: design, the vessel, the charger and an owner's representative. The district has three engineers and no shipbuilding experience. Turner and Simister on contracts as a way to align the objectives of buyer and seller and Thai on the competing goals of public procurement frame the argument that procurement is most of the project.
Where the QSO 349 Module 1 rubric puts the points
The opening QSO 349 thread is marked for a sound account of what procurement contributes to a project, an example that estimates the share of the budget spent with sellers, procurement vocabulary used accurately, attention to how each contract divides risk, awareness of the buyer's own limits, particularly as a public body, research that is cited and applied and replies that push classmates to look at what their projects buy. The top posts explain why the buyer contracted the work out. Marks fall for posts that reduce procurement to purchase orders, skip risk, treat contracts as forms or greet peers without engaging their examples. Grammar and APA citations are part of the score as well.
QSO 349 Module 1 help: the mistakes that cost points
Pick a project and estimate how much of its budget goes to outside sellers: contractors, consultants, equipment and software. Then explain why the organization buys rather than does that work, which purchases are largest or riskiest and what each contract will need to say. Consider who carries the risk if costs rise or the work is late: a fixed price puts more on the seller, a cost-reimbursable contract more on the buyer. If the buyer is public, mention the rules on competition and transparency it must follow. A common mistake is describing procurement as ordering supplies; another is listing contracts without saying what they decide. Close by asking classmates which purchase in their projects could sink the schedule.
Get QSO 349 Module 1 written to your instructions
Paste the QSO 349 Module 1 prompt and describe a project you know. A writer explains how much of it is bought, what procurement decides about scope, cost and risk, how contracts share risk between buyer and seller and what a public or private buyer must settle first, using procurement research, and asks QSO 349 classmates a question. Your first QSO 349 post is free, back in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 349 papers and related BS Operations Management samples
- QSO 349 Module 2 Make-or-Buy Assignment: Designing the Ferry In-House or With a Naval Architect
- QSO 349 Module 3 Project One: The Procurement Management Plan
- QSO 349 Module 4 Discussion: Fixed Price or Cost-Plus for a First-of-Its-Kind Boat?
- QSO 349 Module 5 Source Selection Assignment: Scoring Three Shipyard Proposals
- QSO 349 Module 6 Discussion: Negotiating With the Winning Shipyard
- QSO 349 Module 7 Project Two: Changes, a Battery Delay and Closeout
- QSO 349 Module 8 Discussion: A Losing Shipyard's Protest
- QSO 250 Module 2 Data Sources Assignment: What the Business Already Knows About Its Customers
- OL 215 Module 8 Discussion: Ethics in Everyday Management
- MKT 345 Module 4 Discussion: The Problem With Things Others Touched
- FIN 470 Module 4 Cost of Capital Assignment: A WACC for a Company With No Debt
QSO 349 Module 1 questions, answered
Where can I find a free QSO 349 Module 1 Discussion sample?
This page holds the full QSO 349 Module 1 post: why procurement is most of an invented ferry district's boat replacement and how its contracts share risk.
What is project procurement management?
The processes needed to buy products, services or results from outside the project team: planning purchases, conducting procurements by selecting sellers and controlling contracts through closure.
Why do contracts matter for project risk?
The contract type decides who pays if costs rise or work is late; fixed-price contracts place more cost risk on the seller and cost-reimbursable contracts more on the buyer.
How is public procurement different?
Public buyers must usually follow laws on open competition, transparency, equal treatment of bidders and records, and are accountable to taxpayers and funding agencies.
Who manages contracts on a project?
The project manager works with a contracting officer or procurement specialist who holds authority to sign and change contracts, while technical staff monitor the seller's work.