QSO 349 Module 3 Project One Example

Reviewed by Portia Lambrick, MBA

This QSO 349 Module 3 Project One sample develops a procurement management plan with procurement packages, contract types, statements of work, selection methods, evaluation criteria, a schedule and roles. SNHU QSO 349 (QSO-349) asks for this plan in Module 3; the course covers project contracting for BS Operations Management students. The buyer is the Casco Narrows Ferry District, an invented Maine operator replacing a diesel ferry with a hybrid-electric boat and a charger on a $14.8 million budget. The plan splits the purchase into four contracts, chooses a contract type and selection method for each from the uncertainty of the work and sets dates and decision rights.

CourseQSO 349 Project Contracting and Procurement
ModuleModule 3
Paper typeundergraduate project developing a procurement management plan with procurement packages, contract types, statements of work, selection methods, evaluation criteria, schedule and roles
LengthAbout 1,060 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramBS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 349 Module 3

1

Four Contracts, One Boat: The Procurement Management Plan for the Casco Narrows Hybrid Ferry

[Student Name]

Southern New Hampshire University

QSO 349: Project Contracting and Procurement

Project One: Procurement Management Plan

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe packages, contract types and dates for the Casco Narrows Ferry District in this QSO 349 project are fictional.
2

Four Contracts, One Boat: The Procurement Management Plan for the Casco Narrows Hybrid Ferry

Introduction

Funding of $14.8 million, from a state transportation bond and federal grant money, covers a new hybrid-electric ferry, its mainland charger and the work behind both. The make-or-buy analysis concluded that the district will buy the design, the vessel, the charger and an owner's representative, keeping the owner's requirements and every major decision in-house. This plan sets out how each of those purchases will be made: the packages, contract types, statements of work, selection methods, evaluation criteria, schedule, roles and procurement risks.

What this page is doingStates what the plan covers.
3

Procurement Packages

Procurement packages

PackageBudgetContract typeSelection method
1. Naval architecture design and construction support$900,000Fixed fee for design; time and materials capped at $150,000 for supportQualifications-based selection, then fee negotiation
2. Vessel construction$11,200,000Firm fixed price with economic price adjustment on battery cellsNegotiated request for proposals, best value
3. Shoreside charger and terminal electrical work$1,900,000Firm fixed priceSealed invitation for bids, lowest responsive and responsible bidder
4. Owner's representative$400,000Time and materials, not to exceedRequest for qualifications, then negotiation
District contingency$400,000
Total$14,800,000

The packages follow the kinds of sellers in the market. Naval architecture firms, shipyards, electrical contractors and marine surveyors are different businesses, and combining any two in one contract would shrink the field of bidders. The charger is kept out of the shipyard's contract because its work is on land, under different permits and trades, and because the district's electric utility must coordinate the service upgrade directly with the installer.

What this page is doingSplits the purchase into contracts.
4

Contract Types

Bajari and Tadelis (2001) treat the decision as a trade-off: fixed prices push sellers hard to hold down cost, yet when a design is incomplete and changes are likely, every change must be renegotiated at a cost, so cost-plus contracts suit complex work that cannot be fully specified in advance. Turner and Simister (2001) make a similar point in project terms, arguing that the right contract depends on whether the buyer knows what it wants and whether the seller knows how to make it. The plan applies that reasoning package by package.

The design itself can be specified by its deliverables, so the naval architect works for a fixed fee. Construction support cannot be specified, since no one knows how many questions the yard will ask, so it is time and materials with a cap. The vessel will be bid on a complete contract design approved by the Coast Guard, which makes it well specified enough for a firm fixed price. The one large uncertainty the yard cannot control is the price of battery cells, which has swung widely in recent years. An economic price adjustment clause will move the contract price up or down with a published battery index, limited to 15 percent of the battery system's value, so yards need not pad their bids for it. The charger is standard equipment installed to drawings, which suits a firm fixed price. The owner's representative's workload depends on the yard's progress and problems, so hourly billing under a ceiling the district sets, with monthly reports, fits best.

What this page is doingMatches each type to the uncertainty of the work.
5

Statements of Work

The design statement of work requires concept and contract design, stability and structural calculations, the specification, the drawings needed for Coast Guard plan approval and bid support, with the owner's requirements attached. The vessel statement of work is the approved contract design plus delivery terms: builder's trials, acceptance trials on the route, crew training, spare parts, manuals and a one-year warranty. The charger statement of work covers the charger, the dockside connection, the utility service upgrade and commissioning. The owner's representative statement of work covers plan review, inspection at the yard, progress reporting, witnessing trials and advising on changes and claims.

What this page is doingOutlines what each seller must deliver.
6

Selection Methods and Criteria

In the private construction market examined by Bajari et al. (2009), owners put complicated or loosely specified jobs out to negotiation with a chosen builder far more often than to open bidding, since talking first allows design problems to be settled before a price is agreed. That reasoning guides the plan. The vessel is complex and must be built by a yard with experience the district cannot easily check, so the district will use a negotiated request for proposals and award on best value. Price will carry 25 of 100 points; the technical approach carries 30, experience with similar boats 20, the schedule 15 and past performance the remaining 10. The charger is standard work, so a sealed bid awarded to the lowest responsive and responsible bidder is faster and easier to defend. The naval architect and the owner's representative will be chosen on qualifications first, with the fee negotiated afterward, as is common for professional services.

What this page is doingExplains how sellers will be chosen.
7

Procurement Schedule

Procurement schedule

StepDate
Naval architect selected and under contractFebruary 2027
Contract design complete and submitted for plan approvalDecember 2027
Vessel request for proposals issuedFebruary 2028
Proposals dueApril 2028
Evaluation, negotiation and board awardJune 2028
Charger invitation for bids issuedJuly 2028
Charger contract awardedSeptember 2028
Owner's representative under contractJune 2028
Vessel deliveryMay 2029

The vessel's construction period of eleven months is tight for a new design, and the battery system has a lead time of about seven months, so the request for proposals will require the yard to order cells within 30 days of award. The charger must be commissioned before sea trials at the dock in April 2029.

What this page is doingWorks back from delivery.
8

Roles and Authority

The board awards every contract over $250,000 and approves changes that raise a contract's value by more than 10 percent. The district's procurement officer issues solicitations, keeps the official record and signs contracts and change orders after approval. The project manager, an engineer in the district's office, writes the statements of work, chairs the evaluation committees and approves changes within budget below the board's threshold. Evaluators sign conflict of interest statements before reading proposals.

What this page is doingNames who decides what.
9

Procurement Risks

The main risks are few bidders for the vessel, since only a handful of yards build hybrid ferries; battery prices and lead times; protests from losing bidders; and the requirements that come with federal grant money. Responses include a pre-proposal meeting and yard visits to attract bidders, the price adjustment clause and early cell orders, a written evaluation record and debriefings and a review of every solicitation by the district's counsel and the grant administrator.

What this page is doingLists what could go wrong in buying.
10

References

Bajari, P., McMillan, R., & Tadelis, S. (2009). Auctions versus negotiations in procurement: An empirical analysis. Journal of Law, Economics, and Organization, 25(2), 372-399. https://doi.org/10.1093/jleo/ewn002

Bajari, P., & Tadelis, S. (2001). Incentives versus transaction costs: A theory of procurement contracts. RAND Journal of Economics, 32(3), 387-407. https://doi.org/10.2307/2696361

Turner, J. R., & Simister, S. J. (2001). Project contract management and a theory of organization. International Journal of Project Management, 19(8), 457-464. https://doi.org/10.1016/S0263-7863(01)00051-5

What the QSO 349 Module 3 instructions ask for

QSO 349 Project One usually asks students to develop a procurement management plan for a project. Expect to state what will be procured and why, based on make-or-buy decisions; divide the work into procurement packages; choose a contract type for each, such as firm fixed price, cost-reimbursable or time and materials, and justify it; outline the statement of work; choose a solicitation and selection method and the evaluation criteria; set a procurement schedule linked to the project schedule; define roles and authority; and identify procurement risks and how contracts will be administered. Strong plans link each contract type to how well the work can be specified, explain how sellers will be selected fairly and make the schedule realistic.

How this QSO 349 Module 3 project one example is built

The project plans procurement for the Casco Narrows Ferry District, a fictional Maine operator buying a 149-passenger hybrid-electric ferry and a charger. Four packages are defined: naval architecture by qualifications-based selection on a fixed fee with capped construction support; vessel construction by a negotiated request for proposals, scored on best value, under a firm fixed price with an economic price adjustment on the battery; the charger and terminal electrical work by sealed bid on a fixed price; and an owner's representative paid by the hour up to a fixed ceiling. The schedule works back from a May 2029 delivery. Bajari and Tadelis, Bajari, McMillan and Tadelis and Turner and Simister support the choices.

Where the QSO 349 Module 3 rubric puts the points

Instructors grading QSO 349 Project One look at a clear statement of what will be procured, sensible procurement packages, contract types justified by the nature and uncertainty of the work, statement of work outlines a seller could respond to, appropriate selection methods and announced evaluation criteria, a procurement schedule linked to the project schedule, defined roles and authority and attention to procurement risks. The best plans show how every choice shares risk between buyer and seller. Credit drops when one contract type is used for everything, criteria are vague, the schedule ignores lead times, authority is unclear or the plan copies a template without fitting it to the project. Tables, clarity and APA citations count too.

QSO 349 Module 3 help: the mistakes that cost points

Start from your make-or-buy decisions and list everything you will buy, then group it into packages that a single type of seller can deliver. For each package, ask how completely the work can be specified: if fully, a fixed price usually fits; if not, a cost-reimbursable or time-and-materials contract with controls may be better. Choose how sellers will be selected, by lowest price, best value or qualifications, and write the evaluation criteria and weights before any proposal arrives. Build the schedule backward from when each contract must be in place, allowing time for solicitation, evaluation, negotiation and approvals. Name who can sign and change contracts. A common mistake is choosing contract types by habit; another is forgetting long lead times such as batteries or switchgear.

Get QSO 349 Module 3 written to your instructions

Upload the QSO 349 Project One guidelines and describe your project. A writer drafts the procurement management plan: what will be bought, how it is split into packages, the contract type and selection method for each, statement of work outlines, evaluation criteria, the procurement schedule, roles and risks, with research supporting each choice. Your first QSO 349 project is free; expect it in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 349 papers and related BS Operations Management samples

QSO 349 Module 3 questions, answered

Where can I find a free QSO 349 Module 3 Project One sample?

This page holds the complete QSO 349 Project One: a procurement management plan for an invented ferry district's hybrid boat and charger.

What is a procurement management plan?

The part of the project plan describing how goods and services will be acquired: what is bought, contract types, selection methods, criteria, schedule, roles and how contracts will be managed.

What are the main contract types?

Fixed-price contracts, including firm fixed price and fixed price with incentives or price adjustment; cost-reimbursable contracts, such as cost plus fixed fee; and time and materials.

What is a statement of work?

A narrative description of the products, services or results to be supplied under a contract, detailed enough for sellers to decide whether they can deliver and at what price.

What is best-value source selection?

Choosing a seller by weighing price against non-price factors such as technical approach, experience and past performance, rather than by lowest price alone.