A Fire in the Cell Plant: Change Orders, a Delay Claim and Closeout for the Casco Narrows Ferry Contract
[Student Name]
Southern New Hampshire University
QSO 349: Project Contracting and Procurement
Project Two: Contract Administration and Closeout
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
A Fire in the Cell Plant: Change Orders, a Delay Claim and Closeout for the Casco Narrows Ferry Contract
Introduction
The Casco Narrows Ferry District awarded Bayhead Marine a firm fixed-price contract of $11.16 million in June 2028 to build a 149-passenger hybrid-electric ferry for delivery on May 18, 2029. The contract includes an economic price adjustment on battery cells capped at 15 percent, liquidated damages for late delivery set at $2,500 per calendar day and an excusable delay clause. This project describes how the district administered the contract through construction, decides four change orders and a delay claim, tracks the contract value against the budget and sets out the closeout plan.
Administration Approach
The district's owner's representative, a marine surveyor under a time-and-materials contract, spends two days a week at the yard. The contract sets seven inspection hold points, from hull plating to the battery installation, where work may not continue until the representative has inspected it. Bayhead submits a monthly progress report with a schedule update, and the district's project manager holds a monthly meeting with the yard. Only the district's procurement officer may sign change orders, after approval by the project manager for changes up to 10 percent of the contract value in total and by the board above that.
Ibbs et al. (2001) set out principles for project change management: a culture that neither suppresses nor invites change, recognizing change early, evaluating it before acting, implementing it with documentation and learning from it. The district's change process follows those steps. Either party may submit a change request on a standard form; the representative estimates its cost and schedule effect independently; the project manager decides who caused it under the contract; and the change order is signed before the work proceeds. Bajari and Tadelis (2001) explain why that discipline matters under a fixed price: each change is priced after award, when the buyer has no competing seller, so the buyer must check prices against its own estimate.
Change Orders
Change orders
| Change order | Cause | Price | Time | Decision |
|---|---|---|---|---|
| CO-01. Water-mist fire suppression in battery room | Coast Guard requirement during review of the yard's drawings | $86,000 | 1 week, absorbed | Approved; district pays |
| CO-02. Cabin heating upgrade | District request after crew review | $42,000 | None | Approved |
| CO-03. Standard thruster control panel | District request | minus $31,000 | None | Approved as credit |
| CO-04. Acceleration of battery installation | District choice to recover the delay | $48,000 | Recovers 3 weeks | Approved |
| Total | $145,000 |
CO-01 came from the Coast Guard's review of Bayhead's detailed drawings, which required a water-mist system in the battery room in addition to the approved design's fire separation. The contract design approved by the Coast Guard was the district's, so a requirement added to it is the district's cost, not a risk the yard accepted. The yard priced it at $94,000; the representative's estimate was $81,000, and the parties agreed on $86,000. The week of work was absorbed in the schedule.
CO-02 and CO-03 were requested by the district after its crews reviewed the cabin and wheelhouse. The heating upgrade adds radiant heat to the passenger cabin floor for winter crossings, and the credit replaces an upgraded thruster control panel with the yard's standard one, which the crews preferred. Both were priced from the yard's breakdown and checked against the representative's estimate.
The Battery Delay Claim
In January 2029 a fire at the battery supplier's plant stopped production for seven weeks, and the cells reached the yard nine weeks late. Bayhead resequenced work, completing the wheelhouse, piping and interior before the batteries arrived, and cut the effect on delivery to six weeks. It then submitted a claim for a nine-week extension and $140,000 for extended overhead and resequencing.
The contract's excusable delay clause grants time, but not money, for delays caused by events beyond the seller's control and without its fault or negligence, including fires at a supplier's plant. The district first checked whether Bayhead had done what the contract required: it had ordered the cells 24 days after award, within the 30 days the contract set, and notified the district within five days of learning of the fire. The delay was therefore excusable. The extension, however, should reflect the actual effect on delivery, which Bayhead's own schedule showed to be six weeks, not nine. The district granted a six-week extension, waiving liquidated damages for that period, and denied the $140,000, since the clause does not pay for excusable delays.
Bayhead disputed the denial. Under the contract's disputes clause, the matter went first to a meeting of the project managers and then of the yard's president and the district's general manager. At that meeting the district explained the clause, and Bayhead withdrew the money claim. The parties agreed instead on CO-04: for $48,000, Bayhead would add a second shift on the battery installation and commissioning to recover three of the six weeks. The district chose to buy that time because a delivery after mid-June would push the new ferry into its first summer season untested and require chartering a backup boat at about $15,000 a week.
Contract Value and Budget
The battery price index rose 6 percent between the bid and the cell order, so the price adjustment added $144,000, within the 15 percent cap. The contract value is now $11.16 million plus $145,000 of change orders plus $144,000 of adjustment, or about $11.45 million. That is $249,000 above the $11.2 million vessel budget and is covered by the district's $400,000 contingency, leaving $151,000 for the charger and the remainder of the project. The board was informed of the total at each monthly report, and no board approval was needed, since changes total 1.3 percent of the contract value.
Payments and Retainage
Payment milestones
| Milestone | Share |
|---|---|
| Contract signing | 10% |
| Keel laying | 15% |
| Hull complete | 25% |
| Batteries installed | 20% |
| Launch | 10% |
| Delivery and acceptance | 15% |
| Retainage after closeout | 5% |
Each payment is released only after the representative confirms the milestone. The 5 percent retainage, about $570,000, is held until every punch-list item and warranty document is complete.
Closeout Plan
Closeout begins with acceptance. Builder's trials at the yard test the propulsion, steering and safety systems; acceptance trials on the district's route test speed, the twelve-minute charge at the mainland dock and a full day of crossings. The Coast Guard issues the certificate of inspection that allows the ferry to carry passengers. The representative then compiles a punch list, which the yard must clear within 60 days, and the district checks receipt of as-built drawings, manuals, crew training records, spare parts and warranty certificates, and confirms that every change order and the price adjustment are settled.
After that, the district releases the retainage and makes final payment against the yard's signed release of claims, which confirms that no further claims arise from the contract. The one-year warranty begins on acceptance. The district completes a written evaluation of Bayhead's performance on quality, schedule, cooperation and change pricing. Watt et al. (2010) found that past project performance was among the criteria decision makers weighed most heavily in selecting contractors, so a careful, documented evaluation is useful to the district and to other public buyers. Finally, the procurement officer archives the contract file, including evaluations, change orders and the claim record, for the period the grant requires, and the team records lessons learned, beginning with the value of the 30-day cell order requirement.
References
Bajari, P., & Tadelis, S. (2001). Incentives versus transaction costs: A theory of procurement contracts. RAND Journal of Economics, 32(3), 387-407. https://doi.org/10.2307/2696361
Ibbs, C. W., Wong, C. K., & Kwak, Y. H. (2001). Project change management system. Journal of Management in Engineering, 17(3), 159-165. https://doi.org/10.1061/(ASCE)0742-597X(2001)17:3(159)
Watt, D. J., Kayis, B., & Willey, K. (2010). The relative importance of tender evaluation and contractor selection criteria. International Journal of Project Management, 28(1), 51-60. https://doi.org/10.1016/j.ijproman.2009.04.003
What the QSO 349 Module 7 instructions ask for
QSO 349 Project Two usually asks students to administer a contract after award and plan its closeout. Expect to describe how performance will be monitored, how changes are requested, evaluated, priced, approved and documented, how claims and disputes are handled, how payments are tied to progress and acceptance and how the contract will be closed, including acceptance of deliverables, final payment, release of retainage, warranties, records and a performance evaluation of the seller. Strong projects decide each change and claim by reference to the contract's own clauses, separate changes the buyer caused from risks the seller accepted, track the contract value against the budget and treat closeout as a sequence of obligations rather than a final invoice.
How this QSO 349 Module 7 project two example is built
The project administers the Casco Narrows Ferry District's fixed-price contract with Bayhead Marine, a fictional shipyard building a hybrid-electric ferry. Four change orders are decided: a water-mist system the Coast Guard required in the battery room for $86,000, cabin heating the district requested for $42,000, a $31,000 credit and $48,000 of acceleration the district bought. A fire at the cell supplier delays batteries nine weeks; the yard cuts the impact to six and claims $140,000, and the district grants six weeks with no money under the excusable delay clause. With a $144,000 battery adjustment, the price reaches $11.45 million, inside budget plus contingency. Ibbs, Wong and Kwak, Bajari and Tadelis and Watt, Kayis and Willey inform the plan.
Where the QSO 349 Module 7 rubric puts the points
Instructors grading QSO 349 Project Two look at a clear change control process, change orders evaluated for cost, schedule and responsibility under the contract, claims analyzed against the contract's clauses with a reasoned decision, a dispute resolution path, payments tied to milestones and acceptance, tracking of contract value against budget and a complete closeout plan. Projects that score highest show who caused each change and why that decides who pays. Credit drops when changes are approved without analysis or documentation, claims are paid or denied without reference to the contract, payments run ahead of progress or closeout stops at final payment. Tables, clear writing and APA citations count too.
QSO 349 Module 7 help: the mistakes that cost points
Begin with the contract's own rules: who may order changes, how they are priced, what counts as an excusable delay and how disputes are resolved. For each change, ask what caused it, the buyer, the seller, a regulator or an event no one controls, since the cause usually decides who pays and whether time is added. Price changes from the seller's breakdown and an independent estimate, and record every decision in writing. For a delay claim, check whether the seller did what the contract required and what it did to limit the delay. Track the contract value against the budget after every change. Then plan closeout step by step. A common mistake is paying for delays the seller caused; another is releasing retainage before warranty items are fixed.
Get QSO 349 Module 7 written to your instructions
Upload the QSO 349 Project Two guidelines and your contract scenario. A writer administers it: change requests evaluated and priced, claims and delays analyzed under the contract's clauses, payments and retainage tracked against the budget, disputes routed through the right steps and a closeout plan from acceptance to final release, with research behind each step. Your first QSO 349 project is free, with the finished paper in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 349 papers and related BS Operations Management samples
- QSO 349 Module 1 Discussion: Why Buying the Ferry Is Most of the Project
- QSO 349 Module 2 Make-or-Buy Assignment: Designing the Ferry In-House or With a Naval Architect
- QSO 349 Module 3 Project One: The Procurement Management Plan
- QSO 349 Module 4 Discussion: Fixed Price or Cost-Plus for a First-of-Its-Kind Boat?
- QSO 349 Module 5 Source Selection Assignment: Scoring Three Shipyard Proposals
- QSO 349 Module 6 Discussion: Negotiating With the Winning Shipyard
- QSO 349 Module 8 Discussion: A Losing Shipyard's Protest
- QSO 250 Module 4 Discussion: Can We Trust the Rental Records?
- QSO 345 Module 3 Project One: Scope, Work Breakdown and Schedule
- QSO 355 Module 7 Project Two: Schedule Risk and Crashing Before First Tech
- MKT 229 Module 3 Milestone One: Audiences, Insight and Objectives for Winter Glow
QSO 349 Module 7 questions, answered
Where can I find a free QSO 349 Module 7 Project Two sample?
This page holds the complete QSO 349 Project Two: change orders, a delay claim and closeout for an invented ferry district's shipyard contract.
What is contract administration?
Managing the relationship with the seller after award: monitoring performance, approving changes, making payments, handling claims and disputes and closing the contract.
What is a change order?
A written modification to a contract, signed by authorized parties, that changes the scope, price, schedule or other terms.
What is an excusable delay?
A delay caused by events beyond the seller's control and without its fault, such as natural disasters, that usually entitles the seller to more time but not to more money.
What happens at contract closeout?
The buyer verifies that all work is accepted, settles changes and claims, makes final payment, releases retainage, collects warranties and documents, evaluates the seller and archives the records.