| Course | QSO 620 Six Sigma Quality Management |
|---|---|
| Module | Module 2 |
| Paper type | graduate assignment defining a Six Sigma project with a charter, a process map at the SIPOC level, voice-of-the-customer requirements translated into measurable targets and a business case |
| Length | About 1,020 words, 6 pages |
| Format | APA 7 student paper |
| School | Southern New Hampshire University |
| Program | MS Operations Management |
| Updated | October 2026 |
Free sample paper for QSO 620 Module 2
Between Twelve and Eighteen Inch-Pounds: Defining Cloverdell's Torque Project
[Student Name]
Southern New Hampshire University
QSO 620: Six Sigma Quality Management
Define Phase Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Between Twelve and Eighteen Inch-Pounds: Defining Cloverdell's Torque Project
Introduction
Cloverdell Closures makes caps for many products, but one family generates most complaints: 28-millimeter sports caps for squeeze bottles, made on four 32-cavity injection molds at the Georgia plant. The plant's quality steering group selected this family for Cloverdell's first Six Sigma project because the complaints are costly, the requirement is measurable and the process is contained within one plant. This assignment completes the define phase: it gathers customer requirements, maps the process, sets the scope, states the problem and goal and writes the charter.
Voice of the Customer
The project leader interviewed quality managers at five of the eight bottlers that buy sports caps and reviewed the 23 complaints filed over the past year. The bottlers' words fell into three groups.
Customer statements and the requirements behind them
| What customers said | Underlying need | Measurable characteristic |
|---|---|---|
| "Consumers can't get the cap off" and "kids' teams complain" | Cap opens without excessive force | Removal torque at most 18 inch-pounds |
| "Bottles leak in the case" and "caps back off in shipping" | Cap stays sealed until opened | Removal torque at least 12 inch-pounds; no leaks in drop test |
| "Some lots run fine, others don't" | Consistency from lot to lot | Variation in removal torque within the window |
Removal torque, the twisting force needed to open a capped bottle, measured 24 hours after capping on the customer's standard bottle, became the critical-to-quality characteristic, with a lower limit of 12 and an upper limit of 18 inch-pounds. A drop test, no leaks from six capped bottles dropped from four feet, was added as a secondary requirement. The bottlers' capping machines also affect torque, through the force they apply, but every bottler uses settings specified in Cloverdell's own product sheet, so the cap itself is the right place to start.
SIPOC
SIPOC for 28-millimeter sports caps
| Suppliers | Inputs | Process | Outputs | Customers |
|---|---|---|---|---|
| Resin supplier; colorant supplier; mold maker | Polypropylene resin; colorant; molds; press settings | Dry and blend resin, mold caps, cool, insert seal liner, inspect, pack, palletize | Palletized caps in cases, with lot labels | Eight bottlers of sports drinks |
The process map shows that removal torque depends on the cap's dimensions after cooling, its thread geometry and the liner's fit, which the molding steps determine, and on the customer's capping force, which is outside Cloverdell's process.
Scope
The project covers the molding, cooling and liner insertion of 28-millimeter sports caps on the four molds at the Georgia plant, from resin drying to palletized caps. It does not cover other cap families, the Texas plant, the bottlers' capping machines or the resin supplier's processes, though resin properties may be examined as inputs. Limiting scope this way keeps the project finishable in about six months, and DMAIC is known to work best on problems bounded tightly enough for diagnosis to be completed (de Mast & Lokkerbol, 2012).
Problem Statement
Over the last twelve months, Cloverdell's hourly audit data for 28-millimeter sports caps showed an average removal torque of about 15.6 inch-pounds with a standard deviation of about 1.35, implying that roughly 4 percent of caps, about 25 million a year, fall outside the 12 to 18 inch-pound window, mostly above 18. Customers filed 23 complaints, and 14 production lots were placed on hold for resorting. The audit data have not yet been checked for measurement error, which the measure phase will address.
Business Case
Annual cost of the torque problem
| Cost | Estimate |
|---|---|
| Credits and chargebacks to bottlers | About $280,000 |
| Holding and resorting suspect lots | About $135,000 |
| Scrap of resorted caps | About $55,000 |
| Total | About $470,000 |
The estimate excludes the risk of losing a customer. Two bottlers have said they are qualifying a second supplier, and their combined business is worth about $3.2 million a year in sales.
Goal
The goal is to lift the capability index for removal torque, Cpk, to 1.33 or better within six months, which corresponds to fewer than about 60 caps per million outside the window, and to cut complaints about torque by at least 80 percent within a year. Montgomery and Woodall (2008) note that Six Sigma ties projects to measurable process and financial results, and both goals can be tracked with existing data.
The Charter
Project charter, summary
| Element | Content |
|---|---|
| Project | Reduce variation in removal torque of 28 mm sports caps |
| Sponsor | Georgia plant manager |
| Leader | Quality engineer, trained as a Green Belt, 50% of time |
| Team | Molding supervisor, two press operators, a process technician, a maintenance technician, the lab lead |
| Timeline | Define by month 1; measure by month 2; analyze by month 3; improve by month 5; control by month 6 |
| Goal | Cpk of at least 1.33; torque complaints down 80% within a year |
| Benefit | About $375,000 a year of the $470,000 cost |
Choo et al. (2007) found that the way quality projects are structured shapes how much teams learn, and that projects combining a clear method with room for exploration produce more new knowledge. Including operators and a maintenance technician on the team is intended to bring that practical knowledge in.
Team Agreements
The team agreed on three working rules before the measure phase. First, no change to press settings outside the project's planned tests, so that baseline data reflect normal operation. Second, every proposed cause goes on the cause-and-effect list and is tested with data before anyone acts on it, which protects popular theories from being adopted untested and unpopular ones from being ignored. Third, the team meets weekly for an hour at the press, not in a conference room, so that operators on all three shifts can attend at least part of the meeting.
Risks
The torque data may prove unreliable, which would delay the baseline. Improvements may require mold repairs that take weeks. Operators who have long adjusted presses by feel may resist new settings. And bottlers' capping force may contribute more than assumed, in which case the scope would need to widen.
Conclusion
The project now has one customer requirement, removal torque between 12 and 18 inch-pounds, a narrow scope, a problem statement based on a year of data, a business case of about $470,000 a year and a charter with a goal, a team and a six-month timeline. The measure phase will begin by testing whether the torque readings can be trusted.
References
Choo, A. S., Linderman, K. W., & Schroeder, R. G. (2007). Method and context perspectives on learning and knowledge creation in quality management. Journal of Operations Management, 25(4), 918-931. https://doi.org/10.1016/j.jom.2006.08.002
de Mast, J., & Lokkerbol, J. (2012). An analysis of the Six Sigma DMAIC method from the perspective of problem solving. International Journal of Production Economics, 139(2), 604-614. https://doi.org/10.1016/j.ijpe.2012.05.035
Montgomery, D. C., & Woodall, W. H. (2008). An overview of Six Sigma. International Statistical Review, 76(3), 329-346. https://doi.org/10.1111/j.1751-5823.2008.00061.x
What the QSO 620 Module 2 instructions ask for
Module 2 of QSO 620 puts students in the define seat: they listen to customers, decide which measurable property matters, fence the project in and write the agreement that management signs. Expect to collect customer statements, convert them into critical-to-quality characteristics with numeric limits, sketch suppliers, inputs, process, outputs and customers on one page, write problem and goal statements, set the boundaries of the work, estimate what the problem costs and name a sponsor, a leader and a team. Strong papers quote customers before translating them, give every requirement a number, leave out anything the team cannot finish in about six months, use existing records to size the problem, write a goal with a date and list the risks the team can already see.
How this QSO 620 Module 2 define phase assignment example is built
The assignment defines a Six Sigma project at Cloverdell Closures, a fictional bottle cap maker, for 28-millimeter sports caps made on four 32-cavity molds at its Georgia plant, about 610 million caps a year. Interviews with five bottlers turn complaints into a critical-to-quality requirement, removal torque within a 12 to 18 inch-pound window a day after capping, plus no leaks in a drop test. A SIPOC map sets the scope from resin delivery to palletized caps, leaving customers' capping machines out. The charter states the problem with data, about 4 percent of caps estimated outside the window from audit records not yet verified and about $470,000 a year in complaints, holds and resorting, and sets a goal of a capability index of at least 1.33 within six months. De Mast and Lokkerbol, Montgomery and Woodall and Choo and colleagues inform it.
Where the QSO 620 Module 2 rubric puts the points
The QSO 620 define phase assignment is generally graded on requirements drawn from the voice of the customer, critical-to-quality characteristics with measurable limits, a clear SIPOC map, a scope that is explicit about what is in and out, a problem statement supported by data, a measurable and time-bound goal, a business case in dollars, a complete charter with sponsor, team and timeline and attention to risks. The strongest papers show how a vague complaint became a number the team can measure. Credit drops when requirements are assumed, goals are vague, the scope covers too much, the problem statement includes a cause or solution, costs are guessed or the charter lacks a sponsor. Tables, clear writing and APA citations complete the grade.
QSO 620 Module 2 help: the mistakes that cost points
Talk to customers or read what they have said, and list their complaints in their own words. For each, ask what measurable property of the product or service would fix it, and set limits, for example a range or maximum. Draw a SIPOC map, suppliers, inputs, process, outputs and customers, to agree on where the project starts and stops. Write the problem statement with numbers from existing data: what is wrong, how often and since when, without naming a cause. Estimate what the problem costs. Set a goal that says how much improvement by when. Then complete the charter: sponsor, leader, team, timeline by phase and the main risks. Teams often slip a favored fix into the problem statement, and once it is written there the analysis tends to go looking for proof rather than causes.
Get QSO 620 Module 2 written to your instructions
Share the QSO 620 Module 2 instructions and describe your quality problem. A writer gathers the voice of the customer, translates it into critical-to-quality requirements with targets, maps the process at the SIPOC level, sets scope, writes a problem statement with data, builds the business case and drafts the charter with goal, team, timeline and risks, citing Six Sigma research. Your first QSO 620 paper is free, delivered within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 620 papers and related MS Operations Management samples
- QSO 620 Module 1 Discussion: What Six Sigma Adds
- QSO 620 Module 3 Measure Phase Assignment: A Tester That Could Not Be Trusted
- QSO 620 Module 4 Discussion: Why Adjusting After Every Reading Backfires
- QSO 620 Module 5 Analyze Phase Assignment: The Cavities and Settings Behind the Spread
- QSO 620 Module 6 Improve Phase Assignment: A Designed Experiment on the Molding Press
- QSO 620 Module 7 Discussion: Operators Who Trusted Their Feel
- QSO 620 Module 8 Control Phase Assignment: Control Charts and a Reaction Plan
- QSO 620 Module 9 Final Project: The DMAIC Project Report
- QSO 620 Module 10 Discussion: Keeping the Program Alive After the First Win
- OL 610 Module 3 Milestone One: Employee Relations Assessment
- OL 645 Module 7 Milestone Three: Harassment, Reporting and Retaliation Policy
- ACC 660 Module 4 Discussion: Which EBITDA Add-Backs Should a Controller Sign?
- OL 690 Module 2 Discussion: Who Counts After the Fire?
QSO 620 Module 2 questions, answered
Where can I find a free QSO 620 Module 2 Define Phase Assignment sample?
The complete QSO 620 Module 2 assignment is on this page: a Six Sigma charter for bottle cap removal torque at an invented manufacturer.
What is a project charter in Six Sigma?
A document that states the problem, goal, scope, business case, team, sponsor and timeline of a project and serves as the team's agreement with management.
What is a SIPOC diagram?
A one-page outline of who supplies the process, what goes in, the main steps, what comes out and who receives it, drawn to settle where a project begins and ends.
What is the voice of the customer?
The needs and complaints customers express, gathered through interviews, surveys and complaint records and translated into measurable requirements.
Why should a problem statement avoid naming a cause?
Because the analyze phase exists to find causes with data, and naming one too early can steer the team toward a favored solution.