QSO 620 Module 8 Control Phase Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 620 Module 8 Control Phase Assignment sample designs statistical process control charts, a reaction plan and a control plan that sustain a Six Sigma improvement and reviews the first weeks of results. SNHU QSO 620 (QSO-620) assigns the control phase in Module 8 of the Six Sigma course in its MS Operations Management. The process is cap molding at Cloverdell Closures, an invented bottle cap maker that has just brought torque within its customers' window. The paper sets up the charts and the rules for reading them, tells operators what to do when a signal appears and assigns an owner to every setting that could drift.

CourseQSO 620 Six Sigma Quality Management
ModuleModule 8
Paper typegraduate assignment designing statistical process control charts, a reaction plan and a control plan that sustain a Six Sigma improvement, and reviewing early results
LengthAbout 1,000 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 620 Module 8

1

Fifteen Point Zero Five on the Center Line: Holding Cloverdell's Gain

[Student Name]

Southern New Hampshire University

QSO 620: Six Sigma Quality Management

Control Phase Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe charts, plan and results at Cloverdell Closures in this QSO 620 assignment are invented.
2

Fifteen Point Zero Five on the Center Line: Holding Cloverdell's Gain

Introduction

After the improve phase, confirmation runs put the caps' torque at about 15.05 on average and about 0.70 in spread, for a capability index near 1.40. The gain came from cleaning cooling channels, ending over-adjustment and setting chilled water, cooling time and hold pressure from a designed experiment. Each of those could slip. This assignment designs the charts, reaction plan and control plan that will hold the gain and reports the first eight weeks.

What this page is doingStates the control phase task.
3

Choosing the Charts

Torque is a measurement, and the plant already samples caps hourly, so averages and ranges of small subgroups are a natural choice. Each hour, an operator takes five caps from five different cavities in a rotating sequence that covers all 32 cavities of a mold every seven hours, conditions them and tests them on the repaired tester. Rotating cavities means a cavity problem will eventually appear, while taking the five caps together keeps each subgroup a snapshot of one moment. Woodall (2000) emphasizes that control charts are tools for understanding process behavior over time and that sampling plans should reflect the kinds of change one wants to detect.

What this page is doingMatches charts to the data.
4

Calculating the Limits

Limits were calculated from 25 hourly subgroups collected in the two weeks after the new settings were locked, all running without known problems.

Control limits for removal torque, subgroups of five

ChartCenter lineLower limitUpper limit
Subgroup averageAbout 15.05 inch-poundsAbout 14.11About 15.99
Subgroup rangeAbout 1.63 inch-pounds0About 3.45

The limits come from the average range: for subgroups of five, the average chart's limits sit about 0.58 average ranges either side of the center line, and the range chart's upper limit at about 2.11 average ranges. The average range of 1.63 implies a process standard deviation of about 0.70, matching the confirmation runs.

What this page is doingUses post-improvement data.
5

Control Limits Are Not Specifications

The average chart's limits, about 14.1 to 16.0, are much narrower than the customer's 12 to 18 window. They describe what the process does, not what customers will accept. A subgroup average of 16.5 is well within specification but outside the control limits, and it signals that something has changed, perhaps a chiller drifting warmer, before any cap fails. Drawing specification limits on the chart would hide such changes until they became defects.

What this page is doingExplains the difference.
6

Signal Rules

Operators act on any of three signals: a subgroup average or range beyond its limits; seven consecutive averages sitting on the high side of the center line, or seven on the low side; or two of three consecutive averages in the outer third of the band between the center line and a limit on the same side. These rules balance the chance of a false alarm against the speed of detecting a real shift. Anything else is common-cause variation, and the press is left alone.

What this page is doingDefines what counts as a signal.
7

Reaction Plan

Reaction plan for a torque chart signal

StepActionWho
1Mark the point and note the time; do not adjust the pressOperator
2Check chilled water temperature at the mold inlet against 18 °C, plus or minus 1Operator
3Check that the press recipe shows cooling time 3.8 seconds and the approved hold pressureOperator
4Retest the same five caps on the second tester to rule out a gauge problemOperator
5If no cause is found, take five caps from each cavity on the affected mold within the hourOperator and lab
6If any subgroup average exceeds 17 or falls below 13, hold the last two hours of production and call the shift supervisorOperator
7Record the cause found and the action taken on the chart logOperator

The plan never tells the operator to adjust hold pressure on a single signal, which would bring back the over-adjustment that the project removed.

What this page is doingTells operators what to do.
8

Control Plan

Control plan, 28 mm sports caps

ItemRequirementMethodFrequencyOwner
Removal torque12 to 18 inch-pounds; chart in controlAverages and ranges chart, five capsHourlyPress operators
Chilled water temperature18 °C, plus or minus 1Inlet sensor with alarmContinuousMaintenance
Cooling time and hold pressureLocked recipe valuesRecipe lock; change needs engineer and supervisor sign-offEach changeProcess engineer
Cooling channel conditionNo scale; flow within 10% of newFlow test and descalingQuarterlyMaintenance
Torque testerWithin 2% of referenceCalibration against standardMonthlyLab lead
CapabilityCpk at least 1.33Review of chart dataQuarterlyQuality engineer

Montgomery and Woodall (2008) describe the control phase as the point where gains are handed to the process owner with the means to keep them. The control plan was signed by the molding supervisor, who now owns it, and one of the senior night-shift operators co-owns the torque chart.

What this page is doingCovers inputs and owners.
9

Early Results

In eight weeks, the averages chart showed one signal: in week five, three subgroup averages rose toward the upper limit within two hours. Step 2 of the reaction plan found the chilled water at 22 degrees because a chiller valve had stuck, and the operator called maintenance; the problem was fixed within an hour, before any cap left the window, and the two hours of production made during the fault were retested and passed. No other signals appeared, and no adjustments were made without one. Capability calculated from the eight weeks of data was about 1.38, and no torque complaints were received from bottlers. Wu et al. (2009) caution that capability estimates from limited data carry sampling uncertainty, so the quarterly review will recalculate it with more data.

What this page is doingReviews the first eight weeks.
10

Conclusion

Averages and ranges charts with limits from post-improvement data, clear signal rules and a step-by-step reaction plan now guide operators on the sports cap line, and a control plan assigns an owner to every input behind the original problem. In the first eight weeks the charts caught a chiller fault within an hour, capability held at about 1.38 and complaints stopped. The project is ready to be closed and handed to the molding supervisor. The quality engineer will review the charts with the supervisor monthly for the first six months, then quarterly, and recalculate the limits only if a deliberate process change is made.

What this page is doingSummarizes the control phase.
11

References

Montgomery, D. C., & Woodall, W. H. (2008). An overview of Six Sigma. International Statistical Review, 76(3), 329-346. https://doi.org/10.1111/j.1751-5823.2008.00061.x

Woodall, W. H. (2000). Controversies and contradictions in statistical process control. Journal of Quality Technology, 32(4), 341-350. https://doi.org/10.1080/00224065.2000.11980013

Wu, C.-W., Pearn, W. L., & Kotz, S. (2009). An overview of theory and practice on process capability indices for quality assurance. International Journal of Production Economics, 117(2), 338-359. https://doi.org/10.1016/j.ijpe.2008.11.008

What the QSO 620 Module 8 instructions ask for

The QSO 620 Module 8 assignment usually asks students to complete the control phase of a Six Sigma project. Expect to select control charts suited to the data, determine sampling and subgroups, calculate control limits, define rules for detecting signals, write a reaction plan, develop a control plan that documents what is monitored, how, how often and by whom, plan the handoff to the process owner and verify that the improvement is holding. Strong assignments compute limits from data collected after the improvement, explain why control limits differ from specification limits, control the inputs that caused the problem as well as the output, make the reaction plan specific enough for an operator at 3 a.m., assign every item an owner and report early results with capability.

How this QSO 620 Module 8 control phase assignment example is built

The assignment designs the control phase for removal torque at Cloverdell Closures, a fictional bottle cap maker. Averages and ranges of hourly subgroups of five caps from rotating cavities are charted with limits from 25 subgroups after the improvement: a center of about 15.05 inch-pounds, average-chart limits of about 14.1 and 16.0 and a range-chart upper limit of about 3.45. The paper explains why these limits, not the 12 to 18 specification, are used, sets signal rules and a reaction plan and builds a control plan covering torque, chilled water temperature, cooling time locked in the press recipe, quarterly descaling of cooling channels and monthly gauge calibration, each with an owner. In eight weeks the charts caught a chiller fault within an hour and capability held at about 1.38. Woodall, Wu and colleagues and Montgomery and Woodall inform it.

Where the QSO 620 Module 8 rubric puts the points

Graders of the QSO 620 control phase assignment look for charts suited to the data, sensible subgroups and sampling, limits computed correctly from post-improvement data, a clear explanation of control versus specification limits, well-defined signal rules, a reaction plan operators can follow, a control plan that covers the critical inputs with methods, frequencies and owners, a handoff to the process owner and early results with capability. The strongest papers show the charts catching a real problem quickly. Credit drops when limits come from old data or specifications, only the output is monitored, reaction plans say "investigate" without steps, items have no owner or the improvement is declared sustained without data. Tables, clear writing and APA citations complete the grade.

QSO 620 Module 8 help: the mistakes that cost points

Choose a chart that fits the data: averages and ranges for measurements taken in small subgroups, individuals charts for single readings, and attribute charts for counts or proportions. Take subgroups close together in time so they reflect short-term variation. Collect at least 20 to 25 subgroups after the improvement and calculate limits from them, not from the old process and never from the specification. Write the signal rules you will use, such as a point beyond a limit or a long stretch of points all above or all below the middle. For each signal, tell the operator exactly what to check first, second and third, and when to stop the line. Then list every input that caused the problem and how it will be controlled, how often and by whom. Papers often monitor only the output, so the cause can return unnoticed until the output fails.

Get QSO 620 Module 8 written to your instructions

Share the QSO 620 Module 8 instructions and your improved process. A writer chooses the right control charts, sets subgroups and sampling, calculates limits from post-improvement data, explains signal rules, writes a reaction plan operators can follow, builds a control plan for every key input with owners and frequencies and reviews early results and capability, citing research on process control. Your first QSO 620 paper is free, returned in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 620 papers and related MS Operations Management samples

QSO 620 Module 8 questions, answered

Where can I find a free QSO 620 Module 8 Control Phase Assignment sample?

The complete QSO 620 Module 8 assignment is on this page: control charts and plans for cap removal torque at an invented manufacturer.

Why are control limits not the same as the customer's limits?

Control limits are calculated from how the process itself has been behaving and flag change; the customer's limits state what is acceptable and say nothing about stability.

What is a reaction plan?

Step-by-step instructions telling operators what to check and do when a control chart signals, including when to stop production and whom to call.

What goes into a Six Sigma control plan?

Every output and input that must be watched, with how it is checked, how often, by whom and what happens when it drifts.

Why monitor process inputs as well as outputs?

Because a drifting input, such as a temperature, can be caught and corrected before it causes defects in the output.