QSO 620 Module 6 Improve Phase Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 620 Module 6 Improve Phase Assignment sample plans, runs and analyzes a factorial designed experiment to choose process settings and then confirms the improvement and its capability. SNHU QSO 620 (QSO-620) assigns the improve phase in Module 6 of its MS Operations Management Six Sigma course. The process is cap molding at Cloverdell Closures, an invented bottle cap maker whose torque problem traced to cooling and pressure settings. The paper explains why three factors were tested together rather than one at a time, reads the effects on both the average and the spread, picks settings that meet the goal and checks them with confirmation runs.

CourseQSO 620 Six Sigma Quality Management
ModuleModule 6
Paper typegraduate assignment planning, running and analyzing a factorial designed experiment to choose process settings, then confirming the improvement and its capability
LengthAbout 1,010 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 620 Module 6

1

Eight Runs and Three Center Points: Setting Cloverdell's Molding Conditions

[Student Name]

Southern New Hampshire University

QSO 620: Six Sigma Quality Management

Improve Phase Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe experiment, results and settings at Cloverdell Closures in this QSO 620 assignment are invented.
2

Eight Runs and Three Center Points: Setting Cloverdell's Molding Conditions

Introduction

Three causes came out of the analyze phase: scale in the water passages of a handful of cavities, a cooling time chosen for cold winter water, and operators nudging hold pressure after single readings. Two of these need no experiment. Maintenance descaled the cooling channels on molds 2 and 4, and operators stopped adjusting except on control chart signals. The third requires choosing settings, and the settings interact: chilled water temperature, hold pressure and cooling time all affect how much the caps shrink. This assignment designs and runs an experiment to choose them together.

What this page is doingStates the improve phase task.
3

Factors and Levels

Factors and levels

FactorLow level, coded minus oneHigh level, coded plus oneCenter
A: Chilled water temperature12 °C18 °C15 °C
B: Hold pressure5% below current5% above currentCurrent
C: Cooling time3.2 seconds3.8 seconds3.5 seconds

The levels span the range the plant could run in practice without quality or safety concerns. Chilled water temperature can now be controlled with the plant's new chiller, so it becomes a setting rather than a seasonal accident.

What this page is doingChooses what to test.
4

The Design

Box and Wilson (1951) showed how factorial experiments, which vary several factors together, can efficiently locate better operating conditions, especially when followed by further experiments in the promising direction. A full factorial in three factors at two levels needs eight runs. Three center points were added to check for curvature and estimate pure error. The eleven runs were made in random order on mold 2, after its cooling channels were cleaned. At each run, the press was allowed to stabilize for 20 minutes, and then one cap was taken from each of the 32 cavities, conditioned for 24 hours and tested on the repaired torque system. Each run's response is the average and the standard deviation of torque across the 32 caps.

What this page is doingPlans the runs.
5

Results

Experiment results, average and standard deviation of torque across 32 cavities

RunA waterB pressureC coolingAverage torqueStandard deviation
1minusminusminus15.61.17
2plusminusminus14.20.99
3minusplusminus16.51.17
4plusplusminus16.10.99
5minusminusplus15.00.91
6plusminusplus13.60.73
7minusplusplus15.90.91
8plusplusplus15.50.73
Center points, threezerozerozero15.2 to 15.4About 0.94
What this page is doingReports the runs.
6

Effects

An effect is the difference between the average response at a factor's high level and at its low level.

Estimated effects

EffectOn average torque, inch-poundsOn standard deviation, inch-pounds
A: water temperature, 12 to 18 °CAbout minus 0.9About minus 0.18
B: hold pressureAbout plus 1.4About 0
C: cooling timeAbout minus 0.6About minus 0.26
AB interactionAbout plus 0.5About 0
Other interactionsUnder 0.1Under 0.05

Hold pressure has the largest effect on the average but none on the spread. Warmer water and longer cooling both lower the average and, more importantly, reduce the spread, likely because they let the caps cool more evenly across cavities. The AB interaction means that pressure's effect on the average is larger when the water is warmer, about 1.9 inch-pounds at 18 degrees against 0.9 at 12. Testing one factor at a time from the current settings would have missed this and could have set pressure wrongly. Because the center points sit between every pair of levels, they also test whether the response bends inside the range. The center points averaged about 15.3, close to the average of the eight corner runs, about 15.3, so there is no evidence of curvature within the range tested.

What this page is doingReads what each factor does.
7

Choosing Settings

The strategy is to use the factors that reduce variation, water temperature and cooling time, at the levels that minimize spread, and then use hold pressure, which moves only the mean, to center the process. At 18 degrees and 3.8 seconds, the fitted model predicts a standard deviation of about 0.73 and an average of about 14.6 at current pressure. Raising hold pressure by about 2 percent above current, about 0.47 in coded units, is predicted to bring the average to 15.0. Wu et al. (2009) note that capability depends on both centering and spread; at an average of 15.0 and a standard deviation of 0.73, the predicted Cpk is about 1.37, just above the goal.

What this page is doingUses spread first, then the mean.
8

Confirmation

Three confirmation runs at the chosen settings, on molds 2 and 4 on different days and shifts, with operators from all three crews, gave an average torque of about 15.05 and a standard deviation of about 0.70 across 96 caps. The resulting Cpk is about 1.40, with the nearer limit at the top of the window. Expected caps outside the window fall to a few per million. Montgomery and Woodall (2008) emphasize that Six Sigma improvements must be verified with data before they are adopted, and the confirmation results match the predictions closely.

What this page is doingVerifies the prediction.
9

Costs

Longer cooling adds about 0.3 seconds to a 9.6-second cycle, about 3 percent, which reduces the output of the four molds by the same share. At current demand the molds have about 9 percent spare capacity, so the change costs about $55,000 a year in machine time and energy rather than lost sales. Running the chiller at 18 rather than 12 degrees saves some energy, partly offsetting that cost. If demand ever rises enough to need the lost 3 percent, the plant could recover it by shortening another part of the cycle, such as mold opening, which the team will study as a follow-on; the experiment's results show that cooling time should not be the first place to look.

What this page is doingWeighs what the settings cost.
10

Conclusion

After the cooling channels were cleaned and over-adjustment stopped, a factorial experiment with center points showed that warmer chilled water and longer cooling reduce the spread of torque while hold pressure moves its average, with an interaction that one-factor testing would have missed. Settings of 18 degrees, 3.8 seconds and pressure about 2 percent above current gave confirmed results of a 15.05 average, a 0.70 standard deviation and a Cpk of about 1.40, meeting the project goal at a cost of about 3 percent in cycle time.

What this page is doingSummarizes the improvement.
11

References

Box, G. E. P., & Wilson, K. B. (1951). On the experimental attainment of optimum conditions. Journal of the Royal Statistical Society: Series B (Methodological), 13(1), 1-38. https://doi.org/10.1111/j.2517-6161.1951.tb00067.x

Montgomery, D. C., & Woodall, W. H. (2008). An overview of Six Sigma. International Statistical Review, 76(3), 329-346. https://doi.org/10.1111/j.1751-5823.2008.00061.x

Wu, C.-W., Pearn, W. L., & Kotz, S. (2009). An overview of theory and practice on process capability indices for quality assurance. International Journal of Production Economics, 117(2), 338-359. https://doi.org/10.1016/j.ijpe.2008.11.008

What the QSO 620 Module 6 instructions ask for

QSO 620 Module 6 asks students to fix causes and prove that the fix works. Expect to list candidate solutions, carry out repairs that need no testing, plan a designed experiment for settings that must be chosen together, run it in random order, read its effects and pilot the result. Strong papers pick factors straight from the verified causes, set levels wide enough to reveal effects yet safe to run, add middle-level runs to test for a bend in the response, study what each factor does to the spread as well as the average, look for factors that act differently depending on another factor's level, weigh the chosen settings against cycle time or other costs and finish with fresh runs that confirm the prediction and a new capability figure.

How this QSO 620 Module 6 improve phase assignment example is built

The assignment improves removal torque at Cloverdell Closures, a fictional bottle cap maker, after maintenance clears blocked cooling channels. A two-level factorial experiment with three center points tests chilled water at 12 and 18 degrees Celsius, hold pressure 5 percent below and above the current setting and cooling time at 3.2 and 3.8 seconds, measuring torque across 32 cavities in each run. Hold pressure raises mean torque by about 1.4 inch-pounds, warmer water lowers it by about 0.9 and longer cooling by about 0.6, with a pressure-temperature interaction of about 0.5, and warmer water and longer cooling both reduce the spread. Confirmation runs give a mean of 15.05 and a standard deviation of 0.70, a capability index of about 1.40. Box and Wilson, Wu and colleagues and Montgomery and Woodall inform it.

Where the QSO 620 Module 6 rubric puts the points

The QSO 620 improve phase assignment typically earns credit for solutions tied to verified causes, factors and levels chosen from the analysis, a factorial design with randomization and center points, correct estimation of main effects and interactions, analysis of both mean and variation, a check for curvature, settings chosen with costs in view, confirmation runs and a capability assessment compared with the goal. The strongest papers show an interaction that one-factor-at-a-time testing would have missed. Credit drops when factors are changed one at a time, runs are not randomized, only the mean is analyzed, interactions are ignored, settings are chosen without confirmation or costs such as cycle time are left out. Tables, clear writing and APA citations complete the grade.

QSO 620 Module 6 help: the mistakes that cost points

Fix causes that need no experiment first, such as repairs, so that the experiment studies the process as it will run. Choose a few factors the analysis implicated and set two levels for each, wide enough apart that an effect would show, yet inside what the equipment can safely run. A full factorial design runs every combination; add a few center points, all factors at their middle levels, to check whether the response curves. Randomize the run order. For each run, measure the average and the spread. Estimate each factor's effect and the interactions, and look at which factors move the mean and which reduce variation. Use the factors that reduce variation first, then adjust a factor that moves only the mean to hit the target. Confirm with new runs. Papers often analyze only the average, missing the factors that actually reduce the spread.

Get QSO 620 Module 6 written to your instructions

Share the QSO 620 Module 6 instructions and the factors you need to set. A writer chooses factors and levels, designs a factorial experiment with randomization and center points, analyzes effects on both the mean and the variation, checks for interactions and curvature, selects settings that meet the target, plans confirmation runs and assesses capability and costs, citing research on designed experiments. Your first QSO 620 paper is free, ready in roughly two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 620 papers and related MS Operations Management samples

QSO 620 Module 6 questions, answered

Where can I find a free QSO 620 Module 6 Improve Phase Assignment sample?

The complete QSO 620 Module 6 assignment is on this page: a factorial experiment setting cap molding conditions at an invented manufacturer.

What is a factorial designed experiment?

A test plan that runs each possible pairing of factor settings, letting a team see each factor's own effect and how factors combine, from relatively few runs.

What is wrong with testing one factor at a time?

Because it needs more runs for the same information and cannot detect interactions, where the effect of one factor depends on the level of another.

What are center points in an experiment?

Runs with all factors at their middle levels, used to check whether the response curves rather than changing in a straight line between levels.

What is a confirmation run?

A set of new runs at the chosen settings to verify that the predicted improvement actually occurs before the settings are adopted.