QSO 625 Module 9 Final Project Example

Reviewed by Portia Lambrick, MBA

This QSO 625 Module 9 Final Project sample presents a complex Black Belt project from portfolio selection and measurement validation through advanced analysis, experiments, reliability work and leadership changes to finance-validated results. SNHU QSO 625 (QSO-625) concludes its MS Operations Management Black Belt course with this report. The project cut wrong-item shipments at Pellbrook Fulfillment, an invented warehouse that picks and ships tens of thousands of online orders a day. The report shows how each phase changed the team's understanding, why the problem turned out larger than first thought and how the results were checked independently before anyone claimed them.

CourseQSO 625 Six Sigma for Black Belt Certification
ModuleModule 9
Paper typegraduate final project report presenting a complex Black Belt project with portfolio selection, measurement validation, advanced analysis, experiments, reliability work, leadership changes and finance-validated results
LengthAbout 1,020 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 625 Module 9

1

From Fifty-Two to Fifteen per Ten Thousand: Pellbrook's Mis-Ship Project Report

[Student Name]

Southern New Hampshire University

QSO 625: Six Sigma for Black Belt Certification

Final Project

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingPellbrook Fulfillment, its data, results and savings in this QSO 625 project are invented.
2

From Fifty-Two to Fifteen per Ten Thousand: Pellbrook's Mis-Ship Project Report

Summary

Pellbrook Fulfillment now ships the wrong item in about 15 of every 10,000 orders, against a validated baseline of about 52, a reduction of about 71 percent sustained over three months of control. Client-reported mis-ships, the basis of contract penalties, fell from about 41 to about 12 per 10,000. Finance has validated net benefits of about $1.7 million a year, including productivity gains, after subtracting new costs. The project also changed how the site treats errors: pickers are no longer written up for error counts, and the data have become more honest as a result.

What this page is doingStates the result and how it was checked.
3

Selection and Definition

Scored against eight other candidates on client impact, cost, strategic fit, data, feasibility and need for advanced methods, and tested against three alternative weightings, mis-ships ranked first in every case. Kumar et al. (2009) found project selection to be a major influence on whether Six Sigma succeeds, and the scoring kept the site from starting with overtime, a seasonal planning problem. The charter set a goal of 14 per 10,000 against the returns-based figure of 41, with finance agreeing in advance how savings would be calculated.

What this page is doingExplains why this project.
4

Measurement

An attribute agreement study of the pack-out audit found a Fleiss kappa of about 0.58 among four auditors and about 71 percent agreement with known answers, with subtle size and color swaps missed under poor light. Scan verification, photo standards and brighter stations lifted agreement to a kappa near 0.86. The redesigned audit showed a true mis-ship rate of about 52 per 10,000, so the goal was restated as 17, two-thirds below the true baseline, with the champion's and finance's agreement.

What this page is doingFinds the true baseline.
5

Analysis

A value stream map showed that only about 11 of roughly 400 minutes in an order's day added value and that the third daily pick wave crowded nearly half the orders into the two hours before the last carrier cutoff. Four weeks of full scan verification at packing recorded about 4,200 wrong lines among 2.1 million. A logistic model of the binary outcome, the approach Cox (1958) developed, found that a look-alike in the next slot raised the odds of a mis-pick about 3.4 times, a picker's first 30 days about 2.1 times and the pre-cutoff rush about 1.8 times. Lines next to look-alikes were 18 percent of lines but 41 percent of errors. Comparing the scans with past records showed that about half of all errors had gone unrecorded because pickers fixed them quietly to avoid write-ups.

What this page is doingIdentifies the causes.
6

Leadership

Edmondson (1999) tied team learning to members' confidence that admitting an error will not be held against them. With the site manager's support, error-count write-ups ended; skipping required scans remains a disciplinary matter, but scan-detected errors now lead to coaching on causes. Shown the analysis, pickers named 63 look-alike slots, about two-thirds of them unknown to the item master.

What this page is doingChanges what the data depended on.
7

Improvement

Results of the sixteen-run screening experiment

FactorEffect on mis-picks per 10,000 linesEffect on lines per picker-hour
Scan each item at the pickAbout minus 16About minus 8
Separate look-alikesAbout minus 6No clear effect
Scan and separation togetherAbout plus 5, separation matters less once scanningNo clear effect
Voice-directed pickingNo clear effectAbout plus 10
Carts of 16 ordersNo clear effectAbout plus 8

The resolution V half fraction kept main effects and pairwise interactions apart, and a half-normal plot separated real effects from noise, the approach Daniel (1959) proposed for unreplicated designs. All four useful changes were rolled out to six zones, color-coded totes were dropped, and pick waves were released hourly instead of three times a day, which cut the pre-cutoff error spike from about 80 percent above the daily rate to about 20. A Weibull study of sorter failures set belt replacement at 1,200 operating hours and ended a motor replacement rule that was causing early failures.

What this page is doingTests and implements changes.
8

Results

Results over three months of control

MeasureBaselineControl periodGoal
Mis-shipped orders per 10,000, full auditAbout 52About 1517
Client-reported mis-ships per 10,000About 41About 12
Lines per picker-hourAbout 112About 116No loss
Unplanned sorter lane stops per monthAbout 12About 4
What this page is doingReports the control period.
9

Benefits

Annual benefits and costs, validated by finance

ItemAnnual amount
Penalties and reshipping avoided, client-reported basisAbout $1.37 million
Picking labor saved from higher productivityAbout $350,000
Sorter stops avoidedAbout $180,000
Voice-picking licensesAbout minus $120,000
Scanner lease and supportAbout minus $90,000
Net annual benefitAbout $1.69 million

One-time costs were about $64,000 for re-slotting labor and vibration sensors. Finance calculated penalties avoided only on client-reported mis-ships, the basis of the contract, so the larger reduction in unreported errors is not counted, though it protects client relationships.

What this page is doingShows finance-validated figures.
10

Client Reaction

The five largest clients receive Pellbrook's mis-ship figures monthly. Over the control period, client-reported wrong-item complaints fell by about 70 percent, and two clients that had placed Pellbrook on a performance improvement notice under their contracts lifted it. One client asked Pellbrook to present the project at its own supplier conference. The clients also raised a concern the team had not considered: wrong items caused by clients' own product data, such as a mislabeled barcode, still reach their customers, and Pellbrook now reports those separately so clients can fix them.

What this page is doingChecks the result where it matters.
11

Lessons

Validating the measurement first changed the size of the problem. Data from a workforce that fears punishment cannot be trusted. Flow problems can create quality problems, and leveling the work was the cheapest fix of all. A screening experiment with two responses prevented a change that would have cut errors but slowed picking.

What this page is doingRecords what a future Black Belt should know.
12

Next Steps

Missed carrier cutoffs, the second-ranked candidate, is the next Black Belt project, and the hourly waves have already begun to reduce them. Two Green Belt projects on inventory accuracy and damage claims are under way with Black Belt coaching.

What this page is doingExtends the work.
13

Conclusion

The project cut wrong-item shipments by about 71 percent against a validated baseline, sustained the result for three months and delivered about $1.7 million a year in finance-validated net benefits. It did so by fixing the measurement, the flow and the discipline policy as well as the pick process itself. Closure is requested, with the control plan handed to the picking and packing managers.

What this page is doingCloses the project.
14

References

Cox, D. R. (1958). The regression analysis of binary sequences. Journal of the Royal Statistical Society: Series B (Methodological), 20(2), 215-232. https://doi.org/10.1111/j.2517-6161.1958.tb00292.x

Daniel, C. (1959). Use of half-normal plots in interpreting factorial two-level experiments. Technometrics, 1(4), 311-341. https://doi.org/10.1080/00401706.1959.10489866

Edmondson, A. (1999). Psychological safety and learning behavior in work teams. Administrative Science Quarterly, 44(2), 350-383. https://doi.org/10.2307/2666999

Kumar, M., Antony, J., & Cho, B. R. (2009). Project selection and its impact on the successful deployment of Six Sigma. Business Process Management Journal, 15(5), 669-686. https://doi.org/10.1108/14637150910987900

What the QSO 625 Module 9 instructions ask for

The QSO 625 final project generally asks students to present a Black Belt-level Six Sigma project in full. Expect to explain how the project was selected and defined, how the measurement system was validated, what analysis revealed about causes, which advanced tools were used, how improvements were tested and implemented, what controls sustain them, what results were achieved and how benefits were validated. Strong reports show how findings changed the project along the way, use methods suited to each kind of data, include the leadership and organizational changes the results depended on, report results from a sustained control period, separate gross from net benefits with finance's agreement and draw lessons a future Black Belt could use.

How this QSO 625 Module 9 final project example is built

The project reports the mis-ship project at Pellbrook Fulfillment, a fictional Louisville warehouse. Chosen from nine candidates, it first found the pack-out audit agreeing at a kappa of only 0.58 and redesigned it, raising the measured baseline from about 41 to about 52 wrong orders per 10,000. A value stream map and a logistic regression on 2.1 million pick lines tied errors to look-alike items stored side by side, new pickers and the end-of-day crush, and showed that error-count discipline had hidden about half of all errors. A sixteen-run fractional factorial chose scanning at the pick, look-alike separation, voice picking and larger carts. Over three months of control, mis-ships averaged about 15 per 10,000, with net benefits validated at about $1.7 million a year. Kumar and colleagues, Cox, Daniel and Edmondson inform it.

Where the QSO 625 Module 9 rubric puts the points

Instructors grading the QSO 625 final project expect a justified project selection, a validated measurement system, analysis methods matched to the data, causes supported by evidence, improvements tested with designed experiments, controls with owners, results from a sustained control period, net benefits validated by finance, attention to the organizational changes the results required and lessons for future projects. The strongest reports show how the project's understanding changed as evidence arrived. Credit drops when phases are reported as a checklist, results come from a short pilot, savings are gross or self-certified, leadership issues are left out or the analysis uses methods that do not fit the data. Tables, clear writing and APA citations complete the grade.

QSO 625 Module 9 help: the mistakes that cost points

Lead with the result, the money and how they were checked. Then tell the project in the order it unfolded, emphasizing what each phase changed: a measurement study that revealed undercounting, an analysis that pointed to an unexpected cause, an experiment that showed an interaction. Name the method used at each step and why it suited the data. Include the organizational changes the improvement needed, such as a policy that discouraged reporting. Report results from a control period long enough to show they are holding, against both the original and any restated baseline. Separate gross savings, new costs and net benefits, and say who validated them. End with lessons and next steps. Black Belt reports often read as a tour of tools; the stronger ones show how evidence redirected the project.

Get QSO 625 Module 9 written to your instructions

Send the QSO 625 final project guidelines with the work from your earlier modules. A writer presents the project selection, measurement validation, flow and statistical analysis, experiments, reliability and leadership work as one story, reports controlled results against the goal, shows finance-validated net benefits and sets out lessons and next projects, citing Six Sigma and team research. Your first QSO 625 paper is free, produced within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 625 papers and related MS Operations Management samples

QSO 625 Module 9 questions, answered

Where can I find a free QSO 625 Module 9 Final Project sample?

Read the full QSO 625 Module 9 final project here: a Black Belt report on wrong-item shipments at an invented fulfillment center.

What makes a project Black Belt level?

Its scale, cross-functional scope, the advanced methods it requires and the leadership needed to change how an organization works, not only a process step.

Why might a baseline be restated during a project?

Because validating the measurement system can reveal that the original data undercounted or overcounted the problem, so goals must be set against the true level.

How long should a control period be before results are reported?

Long enough to show the improvement is stable under normal conditions, often three months or more, including busy periods where possible.

How are net benefits different from gross savings?

Gross savings are the costs avoided; net benefits subtract the new costs the project created, such as equipment, licenses and added time.