Free sample paper for QSO 510 Module 3
Bid High, Bid Low or Stay Home: A Decision Tree for Prairie Wind's University Contract
[Student Name]
Southern New Hampshire University
QSO 510: Quantitative Analysis for Decision Making
Decision Tree Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Bid High, Bid Low or Stay Home: A Decision Tree for Prairie Wind's University Contract
Introduction
A university about 30 miles from Cedar Rapids has invited bids for a three-year contract to carry its athletic teams to away games and tournaments. Prairie Wind Coach Lines can bid high, bid low or not bid. Winning would require leasing two more coaches. Its main competitor, a larger regional operator, may bid aggressively to win the account. This assignment structures the decision as a tree, calculates expected values, prices information about the competitor and tests how sensitive the choice is.
Payoffs
Contract payoffs over three years
| Bid | Annual revenue | Annual operating cost | Annual lease for two coaches | Annual profit | Three-year profit |
|---|---|---|---|---|---|
| High | $1,950,000 | $1,500,000 | $192,000 | $258,000 | $774,000 |
| Low | $1,750,000 | $1,500,000 | $192,000 | $58,000 | $174,000 |
Operating costs are estimated from Prairie Wind's cost per mile and hour on similar college work, applied to the university's schedule from the last three seasons. Preparing a bid, including route planning and a site visit, costs about $12,000 whether Prairie Wind wins or not. Losing costs nothing further, since the coaches would be leased only if Prairie Wind wins. The payoffs are not discounted; at an 8 percent rate, the high bid's three-year profit would be worth about $665,000 today, which does not change the comparison.
Probabilities
The key uncertainty is the competitor's strategy. The competitor has bid aggressively in about two of its last five public contracts in the region, so the probability of an aggressive bid is set at 40 percent. Whether Prairie Wind wins depends on its own bid and the competitor's strategy.
Probability of winning
| Prairie Wind's bid | Competitor aggressive, 40% | Competitor not aggressive, 60% | Overall |
|---|---|---|---|
| High | 10% | 52% | 35.2% |
| Low | 55% | 80% | 70.0% |
The win probabilities come from the university's scoring rules, which weigh price at 50 percent and service and safety at 50 percent, and from Prairie Wind's record of winning similar contracts at different price levels. Tversky and Kahneman (1974) warn that judgments of probability are prone to biases such as anchoring, so the estimates were set by three managers independently and averaged, and they are tested below.
Folding Back the Tree
Expected values
| Alternative | Calculation | Expected value |
|---|---|---|
| Bid high | 35.2% × $774,000 minus $12,000 | About $260,000 |
| Bid low | 70.0% × $174,000 minus $12,000 | About $110,000 |
| Do not bid | $0 |
The high bid has the highest expected value. Although it wins only about a third of the time, its margin is more than four times the low bid's, so its expected value is more than twice as large. The low bid wins twice as often but earns so little that it barely covers the effort.
Value of Perfect Information
A consultant who follows the regional bus industry has offered, for $15,000, to find out whether the competitor plans an aggressive bid. Howard (1966) introduced information value theory, which values information by how much better decisions it allows, not by how interesting it is. If Prairie Wind knew the competitor would be aggressive, it would compare a high bid, 10 percent of $774,000, about $77,400, with a low bid, 55 percent of $174,000, about $95,700, and choose the low bid. If it knew the competitor would not be aggressive, it would compare 52 percent of $774,000, about $402,500, with 80 percent of $174,000, about $139,200, and choose the high bid.
With perfect information, the expected value before bid costs is 40 percent of $95,700 plus 60 percent of $402,500, about $279,800. Without it, the best choice, the high bid, has an expected value before bid costs of about $272,400. Knowing the competitor's plan in advance would therefore add only about $7,400 in expected value, or roughly $8,000. Even perfect information would be worth far less than the consultant's $15,000 fee, and a consultant's information would be imperfect. Prairie Wind should not buy it.
Sensitivity
The high bid remains best as long as its expected value exceeds the low bid's. Setting the two equal as the probability of an aggressive competitor varies gives a break-even probability of about 93 percent: only if the competitor were almost certain to bid aggressively would the low bid be better. The decision is also robust to costs: higher operating costs hurt the low bid first, and at about $58,000 more a year the low bid would lose money while the high bid would still earn about $200,000 a year. It is more sensitive to the win probability at the high price; if the chance of winning with a high bid against a non-aggressive competitor fell from 52 percent to about 20 percent, the two bids would be roughly equal.
Risk
Expected value treats a 65 percent chance of winning nothing as acceptable because the winning outcome is large. For Prairie Wind, losing the bid costs only $12,000 and leaves the business as it is, so the downside is small and expected value is a reasonable guide. If winning had required buying coaches rather than leasing them, the risk would deserve more weight. Howard (1988) notes that decision analysis can incorporate attitudes toward risk where outcomes are large relative to the decision maker's resources.
Before Submitting
Three checks should come before the bid goes in, because each could change the numbers in the tree. First, the lease for two coaches should be quoted with a clause ending it if the contract is lost or not renewed; otherwise a loss after the first year would leave Prairie Wind paying $192,000 a year for coaches it does not need. Second, the university's schedule puts many departures on Friday afternoons, when Prairie Wind's drivers are already busy, so the operations manager should confirm that enough drivers can be hired; the linear program later in the course found drivers, not coaches, to be the binding constraint. Third, the bid team should watch for signals of the competitor's strategy, such as a new depot near the campus, and revise the 40 percent estimate if any appear.
Recommendation
Prairie Wind should submit the high bid, at about $1.95 million a year, and should not pay $15,000 for information about the competitor, which could add at most about $8,000 in expected value. The recommendation holds unless the competitor is almost certain to be aggressive or the high bid's chances of winning are far lower than estimated. If Prairie Wind wins, it should lease the two coaches on terms that end with the contract.
References
Howard, R. A. (1966). Information value theory. IEEE Transactions on Systems Science and Cybernetics, 2(1), 22-26. https://doi.org/10.1109/TSSC.1966.300074
Howard, R. A. (1988). Decision analysis: Practice and promise. Management Science, 34(6), 679-695. https://doi.org/10.1287/mnsc.34.6.679
Tversky, A., & Kahneman, D. (1974). Judgment under uncertainty: Heuristics and biases. Science, 185(4157), 1124-1131. https://doi.org/10.1126/science.185.4157.1124
What the QSO 510 Module 3 instructions ask for
The QSO 510 Module 3 assignment usually asks students to analyze a decision under uncertainty with a decision tree. Expect to identify the decision alternatives, the uncertain events and their probabilities, the payoffs for each path, then calculate expected monetary values by folding the tree back from right to left, choose the best alternative, calculate the expected value of perfect information and, in many versions, of sample information, and test how sensitive the choice is to key probabilities or payoffs. Strong assignments justify each probability, include all relevant costs such as preparing a bid, show the calculations, explain what the value of information means for whether to gather more data and identify the probability at which the decision would change.
How this QSO 510 Module 3 decision tree assignment example is built
The assignment builds a decision tree for Prairie Wind Coach Lines, a fictional charter bus company in Cedar Rapids, Iowa, deciding whether to bid high, bid low or not bid on a three-year university athletics contract. A high bid of $1.95 million a year would earn about $774,000 over the contract and a low bid of $1.75 million about $174,000. Win chances depend on whether the main competitor bids aggressively, judged 40 percent likely. After a $12,000 bid cost, the high bid's expected value is about $260,000 against about $110,000 for the low bid. Perfect knowledge of the competitor would be worth only about $8,000, less than a $15,000 consultant's fee, and the high bid stays best unless aggression is over about 93 percent likely. Howard and Tversky and Kahneman inform the analysis.
Where the QSO 510 Module 3 rubric puts the points
The QSO 510 decision tree assignment is commonly graded on a correctly structured tree, alternatives and chance events that reflect the real decision, probabilities and payoffs with stated sources, accurate expected value calculations shown step by step, a correct value of information calculation and its interpretation, sensitivity analysis and a recommendation explained in business terms. The strongest assignments show how the value of information changes whether to gather more data. Credit drops when probabilities appear without basis, costs such as bid preparation are omitted, the tree is folded back incorrectly, the value of information is misread or no sensitivity is shown. Tables, clear writing and APA citations complete the grade.
QSO 510 Module 3 help: the mistakes that cost points
Start by drawing the decision as a square with a branch for each alternative, including doing nothing. After each, draw the uncertain events as circles with branches for their outcomes and probabilities, and write the payoff at the end of each path. Fold back: at each chance node, multiply payoffs by probabilities and add; at each decision node, choose the highest. Then ask what perfect knowledge of the key uncertainty would be worth: the expected value if you could choose after learning it, minus the best expected value without it. Compare that with what information costs. Finally, vary the key probability and find where the best choice changes. A common mistake is forgetting the cost of acting, such as preparing a bid; another is treating a guessed probability as fact.
Get QSO 510 Module 3 written to your instructions
Share the QSO 510 Module 3 instructions and describe your decision. A writer structures the decision tree with alternatives, chance events, probabilities and payoffs, folds it back to expected values, calculates the expected value of perfect or sample information, tests sensitivity and explains the recommendation in plain terms, citing decision analysis research. Your first QSO 510 paper is free, ready within about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.
More QSO 510 papers and related MS Operations Management samples
- QSO 510 Module 1 Discussion: Which Model for Which Decision
- QSO 510 Module 2 Probability Assignment: Breakdowns on the Road
- QSO 510 Module 4 Discussion: What a Demand Forecast Is Worth
- QSO 510 Module 5 Regression Assignment: What Drives Charter Revenue
- QSO 510 Module 6 Forecasting Assignment: Monthly Charter Days
- QSO 510 Module 7 Linear Programming Assignment: Assigning Coaches and Drivers
- QSO 510 Module 8 Simulation Assignment: A Saturday With Three Football Games
- QSO 510 Module 9 Final Project: The Decision Analysis Report
- QSO 510 Module 10 Discussion: Models a Manager Should Not Trust
- OL 690 Module 10 Discussion: Measuring Responsibility When Ratings Disagree
- MKT 645 Module 9 Discussion: Channel Conflict With Offline Partners
- MGT 605 Module 3 Discussion: From Rough Order to Definitive
- OL 635 Module 5 Milestone Two: Analysis and Recommendations
QSO 510 Module 3 questions, answered
Where can I find a free QSO 510 Module 3 Decision Tree Assignment sample?
The complete QSO 510 Module 3 assignment is on this page: a decision tree for an invented charter bus company's contract bid.
What is a decision tree?
A diagram of a decision showing alternatives as branches from decision nodes, uncertain events as branches from chance nodes with probabilities and payoffs at the ends of paths.
What is expected monetary value?
The probability-weighted average payoff of an alternative, calculated by multiplying each outcome's payoff by its probability and adding the results.
What is the expected value of perfect information?
The expected value of deciding after learning an uncertain outcome, minus the expected value of the best decision without that knowledge; the most it is worth paying for information.
What is sensitivity analysis in decision analysis?
Testing how the best decision changes as key probabilities or payoffs vary, often by finding the break-even value at which two alternatives are equally good.