QSO 510 Module 8 Simulation Assignment Example

Reviewed by Portia Lambrick, MBA

This QSO 510 Module 8 Simulation Assignment sample builds a Monte Carlo simulation of an operation with several uncertainties and compares policies on risk and expected cost. SNHU QSO 510 (QSO-510) assigns simulation in Module 8 of the MS Operations Management quantitative analysis course. The operation is a peak football Saturday at Prairie Wind Coach Lines, an invented Iowa charter bus company where breakdowns, missing drivers and last-minute charters can all strike at once. The paper simulates 5,000 Saturdays under nine combinations of spare coaches and standby drivers and finds the combination that best balances expected cost against the risk of a missed game.

CourseQSO 510 Quantitative Analysis for Decision Making
ModuleModule 8
Paper typegraduate assignment building a Monte Carlo simulation of an operation with several uncertainties and comparing policies on risk and expected cost
LengthAbout 1,030 words, 6 pages
FormatAPA 7 student paper
SchoolSouthern New Hampshire University
ProgramMS Operations Management
UpdatedOctober 2026

Free sample paper for QSO 510 Module 8

1

Five Thousand Saturdays: Simulating Spare Coaches and Standby Drivers at Prairie Wind

[Student Name]

Southern New Hampshire University

QSO 510: Quantitative Analysis for Decision Making

Simulation Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe model inputs, policies and results for Prairie Wind Coach Lines in this QSO 510 assignment are invented.
2

Five Thousand Saturdays: Simulating Spare Coaches and Standby Drivers at Prairie Wind

Introduction

On football Saturdays, Prairie Wind Coach Lines runs about 30 trips at once, many to stadiums hundreds of miles away. Three things can go wrong together: a coach can break down, a driver can fail to report and a customer can call on Friday night needing one more coach. Each event alone is manageable, but they combine in ways that simple probabilities do not show. The probability assignment in Module 2 estimated each risk separately; this assignment simulates them together to compare policies of keeping spare coaches and standby drivers.

What this page is doingStates the problem.
3

Inputs

Simulation inputs

InputDistributionBasis
Trip length, round tripTriangular, 150 to 700 miles, most likely 320Last two football seasons
BreakdownsEach trip breaks down with probability from a Poisson rate of 2.2 per 100,000 miles, raised 60% for game-day loads and schedulesRoad call records
Driver no-showsEach of 30 drivers fails to report with probability 2%Driver attendance records
Late add-on charter35% chance of one extra tripFriday-night calls last two seasons

Each run represents one Saturday. Uncovered needs arise from breakdowns and add-on trips, which require coaches, and from no-shows and add-on trips, which require drivers. Spare coaches cover coach needs, standby drivers cover driver needs and any remaining need is subcontracted at about $1,450 per coach. Each spare coach kept ready costs about $180 for the day, and each standby driver about $220.

What this page is doingDescribes the uncertain variables.
4

Model Logic and Trials

For each Saturday, the model draws 30 trip lengths, decides for each trip whether it breaks down, decides for each driver whether that driver reports and decides whether an add-on trip arrives. It then counts coach and driver needs, applies the policy's spares and standby drivers and calculates the number of subcontracted coaches and the day's cost. The model was run for 5,000 Saturdays under each of nine policies, using the same random draws for every policy so that differences reflect the policies, not chance. Running 10,000 trials changed the probabilities by less than one percentage point, so 5,000 is enough.

Kleijnen (2005) describes how simulation experiments should be designed to compare alternatives and to test the sensitivity of results to inputs, rather than run once and read. The nine policies form a simple experiment with two factors, spare coaches and standby drivers, each at zero, one and two.

What this page is doingExplains how the simulation runs.
5

Results

Results of 5,000 simulated Saturdays

Spare coachesStandby driversSaturdays needing a subcontractExpected cost per Saturday
0077%$1,720
0162%$1,470
0257%$1,550
1067%$1,630
1134%$1,030
1220%$970
2064%$1,730
2126%$1,060
227%$920

Without protection, more than three Saturdays in four need at least one subcontracted coach. Neither spares nor standby drivers alone help much, because an add-on trip or a breakdown far away needs both a coach and a driver. Together they work: one spare and two standby drivers bring the chance down to about one Saturday in five, at an expected cost of about $970; two of each cut the chance to about 7 percent and the cost to about $920.

Tversky and Kahneman (1974) found that people misjudge how probabilities combine. Before the simulation, managers guessed that a subcontract was needed on perhaps a quarter of football Saturdays, not three-quarters.

What this page is doingCompares the policies.
6

Sensitivity

Two inputs matter most. If the chance of a late add-on charter rises from 35 to 50 percent, two spares and two standby drivers cost about $970 a Saturday against about $1,055 for one spare, and the chance of a subcontract with one spare rises to about 25 percent, so the case for the second spare grows. If the breakdown rate is half what was assumed, one spare and two standby drivers costs about $820 against about $900 for two spares, and one spare is clearly enough. The driver no-show rate matters less, because two standby drivers cover most absences across the range tested.

What this page is doingTests the key inputs.
7

Validating the Model

No simulation deserves trust until it has been compared with what actually happened, so the no-protection policy was compared with the 22 football Saturdays of the last two seasons, when Prairie Wind kept no spare coach or standby driver. The company subcontracted at least one coach on 16 of those Saturdays, about 73 percent, against 77 percent in the model, and an average of about 1.3 coaches a Saturday, against about 1.4 in the model. With only 22 real Saturdays, a difference of that size is well within what chance would produce, so the model's inputs appear reasonable. The model may slightly overstate risk because it treats breakdowns on game days as 60 percent more likely, a figure based on a small number of road calls.

The model also leaves out some possibilities. It allows at most one add-on charter, though twice last season a customer asked for two. It treats breakdowns as independent, though a cold snap could raise them across the fleet at once. And it assumes the affiliated operator can always supply coaches. Each of these omissions makes the simulated risk lower than the real one, which strengthens the case for protection.

What this page is doingCompares it with last season.
8

Choosing a Policy

Howard (1988) notes that decision analysis must reflect the decision maker's attitude toward risk when bad outcomes matter beyond their cost. A subcontracted coach may arrive late or in poor condition, and a university team that misses warm-ups will remember. Two spares and two standby drivers have the lowest expected cost and the lowest risk, but the second spare coach is idle on about 93 percent of Saturdays and ties up a coach that could be rented. One spare and two standby drivers costs only about $50 more per Saturday on average while freeing a coach. The Module 7 optimization pointed the same way, finding the driver roster to be the binding resource.

What this page is doingWeighs cost against risk.
9

Recommendation

On football Saturdays, Prairie Wind should keep one spare coach ready and two standby drivers on call, cutting the chance of needing a subcontract from about 77 percent to about 20 percent. On the few Saturdays with three or more home games among its customers, or when an add-on is already likely, it should add a second spare coach.

What this page is doingStates the policy.
10

References

Howard, R. A. (1988). Decision analysis: Practice and promise. Management Science, 34(6), 679-695. https://doi.org/10.1287/mnsc.34.6.679

Kleijnen, J. P. C. (2005). An overview of the design and analysis of simulation experiments for sensitivity analysis. European Journal of Operational Research, 164(2), 287-300. https://doi.org/10.1016/j.ejor.2004.02.005

Tversky, A., & Kahneman, D. (1974). Judgment under uncertainty: Heuristics and biases. Science, 185(4157), 1124-1131. https://doi.org/10.1126/science.185.4157.1124

What the QSO 510 Module 8 instructions ask for

The QSO 510 Module 8 assignment usually asks students to build a simulation model, often Monte Carlo, for a business problem with uncertain inputs. Expect to identify the uncertain variables and choose distributions for them, define the model's logic and outputs, run many trials, summarize results with averages, ranges and probabilities, compare alternative policies or decisions and test how results change with key inputs. Strong assignments base distributions on data or explained judgment, run enough trials for stable results, report risk measures such as the probability of a bad outcome as well as averages, compare several policies under the same random conditions and test sensitivity to the inputs that matter most.

How this QSO 510 Module 8 simulation assignment example is built

The assignment simulates 5,000 peak football Saturdays at Prairie Wind Coach Lines, a fictional charter bus company in Cedar Rapids, Iowa. Each run draws trip lengths, breakdowns at a game-day rate, a 2 percent chance of each of 30 drivers not reporting and a 35 percent chance of a late add-on charter. Without a spare coach or standby driver, about 77 percent of Saturdays need at least one subcontracted coach, at an expected cost of about $1,720. One spare coach with two standby drivers cuts the chance to about 20 percent and the cost to about $970; two spares and two standby drivers reach about 7 percent and $920. One spare and two standby drivers is recommended. Kleijnen, Howard and Tversky and Kahneman inform the analysis.

Where the QSO 510 Module 8 rubric puts the points

The QSO 510 simulation assignment is commonly graded on clearly identified uncertain inputs with justified distributions, a correct and explained model logic, enough trials for stable results, results summarized with averages, ranges and probabilities, policies compared fairly, sensitivity tested on key inputs and a recommendation that weighs cost against risk. The strongest assignments show why a simulation was needed instead of a formula. Credit drops when distributions are arbitrary, the model is run once or a few times, only averages are reported, policies are compared under different random draws or no sensitivity is tested. Tables, clarity and APA citations complete the grade.

QSO 510 Module 8 help: the mistakes that cost points

List the uncertain things in your process and, for each, choose a distribution from data or reasoned judgment: Poisson for rare events, binomial for yes-or-no outcomes among many trials, triangular when you know a minimum, likely value and maximum. Write the model's logic step by step: what happens in one run and what result it produces, such as cost or whether a trip is missed. Run thousands of trials and record the results. Compare policies using the same random numbers, so differences come from the policies, not luck. Report the average, the range and the chance of a bad outcome. Then change the key inputs and see whether the best policy changes. A common mistake is reporting only an average; another is running too few trials.

Get QSO 510 Module 8 written to your instructions

Share the QSO 510 Module 8 instructions and describe the process you need to simulate. A writer defines the uncertain inputs and their distributions, builds the simulation logic, runs enough trials, compares policies on expected cost and risk, tests sensitivity to key inputs and explains the recommendation, citing simulation research. Your first QSO 510 paper is free and arrives in about two days. The paper above is an original model document written by our desk, not a submitted student paper and not an official Southern New Hampshire University document.

More QSO 510 papers and related MS Operations Management samples

QSO 510 Module 8 questions, answered

Where can I find a free QSO 510 Module 8 Simulation Assignment sample?

The complete QSO 510 Module 8 assignment is on this page: a Monte Carlo simulation of a peak Saturday at an invented charter bus company.

What is Monte Carlo simulation?

A method that runs a model many times with inputs drawn at random from their distributions, producing a distribution of outcomes and the probabilities of results.

How many simulation trials are enough?

Enough that rerunning with twice as many trials moves the averages and probabilities by only a trivial amount, which for business models often means thousands.

Why use simulation instead of formulas?

Because when many uncertain events interact, such as breakdowns, absences and extra demand, formulas become unwieldy, while simulation handles the combinations directly.

What are common random numbers in simulation?

Using the same random draws when comparing policies, so that differences in results reflect the policies rather than chance.